SUBJECT: Consent Agenda
Title
A Resolution of the Board of Trustees of the Town of Erie Approving a Construction Contract with GoodLand Construction, Inc., for the Erie Parkway Reuse Waterline Improvements
Body
DEPARTMENT: Public Works
PRESENTER: Todd Fessenden, Public Works Director
David Pasic, Town Engineer
FISCAL SUMMARY:
Cost as Recommended: $590,484.00
Balance Available (2021 Funds): $903,000.00
Budget Line Item Number: 500-70-110-605000-100374
New Appropriation Required: No
STAFF RECOMMENDATION:
Recommendation
Approve the Resolution to award said contract, authorize the appropriate Town officer to execute said contract, and authorize staff to expend construction and contingency funds.
End
SUMMARY AND BACKGROUND OF SUBJECT MATTER:
Constructing this reuse waterline will provide a connection to a secondary reuse water source at Colliers Hill Tank for the irrigation of Erie Community Park.
In May 2021, the Town Administrator authorized a professional services agreement with Murraysmith, Inc. in the amount not-to-exceed $97,000. The work included completion of an existing conditions survey, design and construction documents, bidding support, and construction administration for a new 12-Inch Reuse Waterline to be located in Erie Parkway between South Briggs Street and Powers Street. The design has been completed.
A request for construction bids was posted on Bidnet Direct for the Erie Parkway Reuse Waterline Improvements on August 25, 2021. A virtual non-mandatory pre-bid meeting was held on September 1, 2021.
The following bids were received on September 15, 2021:
Bid Information:
Contractor Bid Amount Bid Bond included
GoodLand Construction, Inc. $ 536,804.00 Yes
American West Construction, LLC $ 669,180.00 Yes
Brannan Sand & Gravel Company $ 702,892.86 Yes
BT Construction, Inc. $1,186,597.00 Yes
The Engineer's Estimate was $ 505,000.00
The low bidder is GoodLand Construction, Inc. Their ref...
Click here for full text