Town of Erie
File #: 20-075    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 1/18/2020 In control: Town Council
On agenda: 1/28/2020 Final action:
Title: A Resolution of the Board of Trustees of the Town of Erie Approving the Third Amendment to the Lynn R. Morgan Water Treatment Facility Expansion CMAR Contract With Garney Companies, Inc.
Sponsors: Public Works
Attachments: 1. Resolution, 2. Amendment, 3. Location Map 012120
Related files: 18-100, 19-078, 20-058, 20-237
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
SUBJECT: CONSENT
Title
A Resolution of the Board of Trustees of the Town of Erie Approving the Third Amendment to the Lynn R. Morgan Water Treatment Facility Expansion CMAR Contract With Garney Companies, Inc.
Body

DEPARTMENT: Public Works

PRESENTER/PREPARER: Todd Fessenden, Public Works Director
Wendi Palmer, Civil Engineer

FISCAL INFORMATION:
Cost as Recommended: $184,915
Balance Available: $1,417,850
Fund: Water
Budget Line Item Number: 500-70-110-605000-100258(with supplemental appropriation)
New Appropriation Required: No

STAFF RECOMMENDATION:
Recommendation
Approve the Resolution to amend said agreement, authorizing the appropriate Town officer to execute said agreement and authorize staff to expend budgeted funds.
End
SUMMARY AND BACKGROUND OF SUBJECT MATTER:
The 2020 Water Fund Budget has funds appropriated for constructing the Water Treatment Plant Expansion.

At the February 26, 2019 Board Meeting, the Board approved Amendment 1, which allowed for the early procurement of membranes.

At the May 14, 2019 Board Meeting, the Board approved Amendment 2 to the CMAR Contract with Garney for authorization for the Guaranteed Maximum Price (GMP) for the Water Treatment Plant Expansion.

As part of the Water Treatment Plant Expansion, a new 30-inch waterline was designed to extend to the south property line of the water treatment plant site. This design was coordinated to connect to the Zone 3 Waterline Extension Phase 2. The design for the Zone 3 Waterline Extension Phase 2 was awarded at the March 13, 2018 Board Meeting.

At this time it is necessary to extend the Zone 3 Waterline beyond the southerly property line of the water treatment plant to a location south of Marfell Street. This extension will enable Rex Ranch Filing 2 to proceed with their site construction without being negatively impacted with the Zone 3 Waterline construction.

The design of the entire second phase of the Zone 3 Waterline Extension is nearing completion...