Title: A Resolution of the Board of Trustees of the Town of Erie Approving the Third Amendment to the Lynn R. Morgan Water Treatment Facility Expansion CMAR Contract With Garney Companies, Inc.
Sponsors: Public Works
Attachments: 1. Resolution, 2. Amendment, 3. Location Map 012120
Related files: 18-100, 19-078, 20-058, 20-237
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: CONSENT 

Title

A Resolution of the Board of Trustees of the Town of Erie Approving the Third Amendment to the Lynn R. Morgan Water Treatment Facility Expansion CMAR Contract With Garney Companies, Inc.

Body

 

DEPARTMENT:                                          Public Works

 

PRESENTER/PREPARER:                     Todd Fessenden, Public Works Director

                                                                                    Wendi Palmer, Civil Engineer

 

FISCAL INFORMATION:

Cost as Recommended:                                          $184,915

Balance Available:                                                               $1,417,850

Fund:                                                                                                         Water

Budget Line Item Number:                      500-70-110-605000-100258(with supplemental appropriation)

New Appropriation Required:                     No

 

STAFF RECOMMENDATION:

Recommendation

Approve the Resolution to amend said agreement, authorizing the appropriate Town officer to execute said agreement and authorize staff to expend budgeted funds.

End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

The 2020 Water Fund Budget has funds appropriated for constructing the Water Treatment Plant Expansion. 

 

At the February 26, 2019 Board Meeting, the Board approved Amendment 1, which allowed for the early procurement of membranes.

 

At the May 14, 2019 Board Meeting, the Board approved Amendment 2 to the CMAR Contract with Garney for authorization for the Guaranteed Maximum Price (GMP) for the Water Treatment Plant Expansion.

 

As part of the Water Treatment Plant Expansion, a new 30-inch waterline was designed to extend to the south property line of the water treatment plant site.  This design was coordinated to connect to the Zone 3 Waterline Extension Phase 2.  The design for the Zone 3 Waterline Extension Phase 2 was awarded at the March 13, 2018 Board Meeting.

 

At this time it is necessary to extend the Zone 3 Waterline beyond the southerly property line of the water treatment plant to a location south of Marfell Street. This extension will enable Rex Ranch Filing 2 to proceed with their site construction without being negatively impacted with the Zone 3 Waterline construction.

 

The design of the entire second phase of the Zone 3 Waterline Extension is nearing completion. Town Staff is working with multiple entities to secure the easements for the waterline extension, which are needed prior to preparing bid documents. Once all easements are secured the project will be bid and the remainder of the waterline will be constructed after the construction contract is approved by the Board. 

 

Due to the complexity of finalizing easements, Staff believes it is in the Town’s best interest to add the extension of the 30-inch waterline south through the Rex Ranch Development to the CMAR project so it can be constructed with the existing onsite 30-inch waterline extension.

 

In addition to this resolution, on the agenda tonight is a resolution for approval a Permanent Utility Easement Agreement, 20-058, which is needed for the extension of the 30-inch waterline through the Rex Ranch Development.

 

Project Construction Cost

                     Preconstruction Phase Services                                                               $       24,210

                     Amendment 1 (19-078)                                                                                    $  2,011,057

                     Amendment 2 (19-222)                                                                                    $  8,750,768

                     Amendment 3 (20-075)                                                                                    $     184,915

                     Total Cost for CMAR                                                                                    $10,970,950

 

Project Design and Administrative Costs

Design Services (18-187)                                                                                    $     459,116

                     Design Services Contingency (18-187)                                          $       65,884

                     Construction Administration (19-223)                                          $      806,722

                     Total Cost Design & Administration                                          $    1,331,722

 

Remaining Contingency for Construction (2.4%)                     $       265,085                                                               

 

Total Project Cost                                                                                                                              $   12,567,757

                                                                                    

Original Water Treatment Plant Expansion Project Schedule

                     Notice of Award                                                               May 15, 2019

                     Notice to Proceed                                                               May 22, 2019

                     Membrane Complete                                          April, 2020

                     Construction Complete                                          September, 2020

 