Town of Erie
File #: 19-367    Version: 1 Name:
Type: Consent Agenda Status: Passed
File created: 8/2/2019 In control: Town Council
On agenda: 8/13/2019 Final action: 8/13/2019
Title: A Resolution of the Board of Trustees of the Town Of Erie Approving the Construction Management At-Risk (CMAR) Contract with Archer Western Construction, LLC for the North Water Reclamation Facility Expansion in the Amount of $255,000
Sponsors: Public Works
Attachments: 1. Resolution, 2. CMAR Contract
Related files: 18-179, 20-459

SUBJECT: CONSENT

Title

A Resolution of the Board of Trustees of the Town Of Erie Approving the Construction Management At-Risk (CMAR) Contract with Archer Western Construction, LLC for the North Water Reclamation Facility Expansion in the Amount of $255,000                     

Body

 

DEPARTMENT:                                          Public Works

 

PRESENTER/PREPARER:                     Todd Fessenden, Public Works Director

                                                                                    Wendi Palmer, Civil Engineer

 

FISCAL INFORMATION:

Cost as Recommended:                                          $   255,000

Balance Available:                                                               $4,575,100

Fund:                                                                                                         Wastewater

Budget Line Item Number:                                           510-70-110-605000-100267

New Appropriation Required:                     No

 

STAFF RECOMMENDATION:

Recommendation

Approve the Resolution to award said contract, authorize the appropriate Town officer to execute said contract, and authorize Staff to expend contracted funds.

 

End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

The 2019 Wastewater Fund Budget has funds appropriated for the design and construction of the North Water Reclamation Facility Expansion. 

 

At the June 12, 2018 Board Meeting, the Board Authorized the Award of a Consultant Contract to HDR Engineering, Inc. for the North Water Reclamation Facility Master Plan and Preliminary Expansion Design.

 

At the April 9, 2019 Board Meeting, the Board adopted the North Water Reclamation Facility Expansion Master Plan and awarded a Professional Services Agreement to HDR Engineering, Inc. for the design of the expansion.  As you may recall, at that time the Board was notified that staff anticipated bringing a Construction Manager At Risk (CMAR) contract to the Board for approval.

 

The Town requested proposals for a CMAR from six contractors on June 14, 2019. Proposals were due July 11, 2019, and three contractors submitted proposals. Staff reviewed the three proposals and selected two contractors for interviews.  Staff conducted interviews on July 19, 2019 and based on the selection criteria selected Archer Western, LLC. Archer Western’s price for the design phase is $255,000. 

 

In addition to CMAR being a good fit for the project goals, it also can allow for early procurement of equipment prior to the final design of the expansion, ensuring the long lead time for equipment doesn’t slow down the schedule, and to ensure the final design fits the specific equipment needed for the expansion.

 

Staff anticipates bringing to the Board of Trustees for authorization up to four amendments to the CMAR Contract regarding procurement and delivery of process equipment, construction of solids treatment process, and the balance of the work for the Guaranteed Maximum Price (GMP) for the North Water Reclamation facility Expansion.

 

ATTACHMENTS:                      

 

a.                     Resolution

b.                     CMAR Contract