Town of Erie
File #: 18-338    Version: 2 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 9/14/2018 In control: Town Council
On agenda: 9/25/2018 Final action:
Title: A Resolution Of The Board Of Trustees Of The Town Of Erie Approving A Construction Contract With Colt & Steel For Construction Of The Bike Parking Plaza In The Amount Of $43,190.12.
Attachments: 1. Bike Parking Plaza Rendering, 2. Construction Contract, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
SUBJECT: Consent Agenda
Title

A Resolution Of The Board Of Trustees Of The Town Of Erie Approving A Construction Contract With Colt & Steel For Construction Of The Bike Parking Plaza In The Amount Of $43,190.12.
Body
DEPARTMENT: Parks & Recreation

PRESENTER: Farrell Buller, Acting Town Administrator

FISCAL INFORMATION:
Cost as Recommended: $45,349.63
Balance Available: $64,400.00
Budget Line Item Number: 100-50-110-605000-100141
New Appropriation Required: No

STAFF RECOMMENDATION:
Recommendation

Approve Colt & Steel to serve as general contractor for the Bike Park Plaza construction project
End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

In the fall of 2017, the Board of Trustees and town staff realized a need for more bicycle parking in downtown Erie. It has been the Town's and Board of Trustees vision to create a dedicated and attractive space for bicycle parking downtown and give residents more options for bicycle parking. During the summer of 2018, the Board of Trustees appropriated additional money from the general fund to complete construction of the Bike Plaza. Town staff worked with Wenk Associates to prepare construction documents and went out to bid.

Construction Contract
On August 8, 2018 an invitation to bid was released and three bids were received as shown below:
Colt & Steel Corporation $43,190.12
Site Work Solutions $71,506.70
KECI Colorado, Inc. $95,850.00

Analysis completed by staff it has been determined that Colt & Steel Corporation is the best overall contractor to complete the project based on the following factors:

* Bid amount
* Past work history/experience
* Interview with staff




Project Budget Summary
The following is a summary of the total project costs and source of funding:

Costs:
Construction Contract $43,190.12
Contingency (10%) $ 4,319.01
Total $47,509.13

Funding:
100-50-110-605000-100141 $64,400.00

Once ap...

Click here for full text