Town of Erie
File #: 17-449    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 11/30/2017 In control: Town Council
On agenda: 12/12/2017 Final action:
Title: A Resolution of the Town of Erie Authorizing a Construction Contract to Richdell Construction, Inc. for the Serene Park Construction Project in the Amount of $1,174,000.00; And Setting Forth Details In Relation Thereto.
Sponsors: Parks & Recreation, Farrell Buller
Attachments: 1. Serene Park Master Plan Renderings, 2. Richdell Construction, Inc Bid, 3. Richdell Construction Agreement.pdf, 4. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
SUBJECT: Consent
Title

A Resolution of the Town of Erie Authorizing a Construction Contract to Richdell Construction, Inc. for the Serene Park Construction Project in the Amount of $1,174,000.00; And Setting Forth Details In Relation Thereto.

Body
DEPARTMENT: Parks & Recreation

PRESENTER: Farrell Buller, Parks & Recreation Director

FISCAL INFORMATION:
Cost as Recommended: $ 1,291,400.00
Balance Available: $ 722,000.00 (Parks Improvement Impact Fund)
Budget Line Item Number: 320-50-110-605000-100163
New Appropriation Required: Yes $ 569,400.00


STAFF RECOMMENDATION:
Recommendation

Approve resolution authorizing a Construction Contract to Richedell Construction, Inc. for the Serene Park Construction Project And Authorizing the Town Administrator to sign said contract.
End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

On February 23, 2016 the Board of Trustees authorized the Town to enter into an agreement with Community Development Group (CDG) to share design costs for the Colliers Hill Neighborhood Park #1. On September 13, 2016 staff presented the site master plan to the Board of Trustees and were given approval to proceed with the completion of construction documents.

With the completion of the construction documents an invitation to bid was released on
September 12, 2017. A bid opening was held on October 23, 2017 with the following three bids received:
Arrow J Landscape & Design, Inc. $1,225,675.00
Goodland Construction, Inc. $1,311,365.00
Richdell Construction, Inc. $1,174,000.00
American Civil Constructors $1,270,000.00

After reviewing all bids and supplemental information staff been determined that Richdell Construction, Inc. is the best overall contractor to complete the project based on the following factors:

* Bid amount
* Past work history/experience
* Completion of similar projects


Project Budget Summary
The following is a summary of the total project costs and source of funding:
...

Click here for full text