Town of Erie
File #: 16-312    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 8/11/2016 In control: Town Council
On agenda: 8/23/2016 Final action:
Title: Consideration of A Resolution Authorizing Award of a Construction Contract To Fiore & Sons, Inc., For the Zone 3 Waterline Improvement Phase1A Project In The Amount of $60,057; And Setting Forth Details In Relation Thereto.
Attachments: 1. Zone3WaterlinePhase1A.pdf, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
SUBJECT: CONSENT AGENDA
Title

Consideration of A Resolution Authorizing Award of a Construction Contract To Fiore & Sons, Inc., For the Zone 3 Waterline Improvement Phase1A Project In The Amount of $60,057; And Setting Forth Details In Relation Thereto.

Body
DEPARTMENT: Public Works

PRESENTER/PREPARER: Gary Behlen, Public Works Director
Russell Pennington, Deputy Public Works Director
Wendi Palmer, Civil Engineer

FISCAL INFORMATION:
Cost as Recommended: $ 72,000
Balance Available: $ 4,934,390
Fund: Water
Budget Line Item Number: 500-70-110-605000-100135
New Appropriation Required: No

STAFF RECOMMENDATION:
Recommendation
Approving the Resolution to award said contract, authorizing the appropriate Town officer to execute said contract, authorizing Staff to expend contracted funds and contingency funds.

End
SUMMARY AND BACKGROUND OF SUBJECT MATTER:
The 2016 budget includes funds to design and construct improvements to the Zone 3 Water System. A new pipeline is under design to provide a new connection to the east of County Line Road to provide additional capacity to fill the new 4 MG water storage tank. In addition to this connection, another connection is needed at Marfell Drive to the existing 30-inch Zone 3 waterline just east of the Water Treatment Plant. This connection is critical for the zone 3 water system. Zone 3 water system provides water to the Orchard Glenn area and Flatiron Meadows. This new connection will be a second point of connection. Because of the increase building in this area it is critical to make these improvements at this time.

The Town requested costs for this connection from four contractors. The following three contractors submitted bids.

Bid Information:
Contractor Bid Amount
Fiore & Sons, Inc. $ 60,057.00
BT Construction, Inc. $ 62,145.00
American West Construction, LLC $ 65,325.00


The Town has developed a good working relationship with Fiore & Sons, Inc. ...

Click here for full text