SUBJECT:
Title
A Resolution of the Town Council of the Town of Erie Approving a First Amendment to an Agreement for Services with RockSol Consulting Group Inc. for Construction Management Services
Department
DEPARTMENT: Public Works
Presenter
PRESENTER(S): David Pasic, Public Works Director
Wendi Palmer, Civil Engineer
end
Time
TIME ESTIMATE: 0 minutes
end
For time estimate: please put 0 for Consent items.
Fiscal
FISCAL SUMMARY:
Cost as Recommended: $6,663
$6,663
Balance Available: $327,582.51
$351,746.00
Fund Transportation Impact Fund
Line Item Number: 300-70-110-605000-100389
300-70-110-605000-100093
New Appropriation Required: No
Policy
POLICY ISSUES:
Whether to use budgeted funds for needed additional construction management scope to complete the project.
Recommendation
STAFF RECOMMENDATION:
Approve the Resolution approving the First Contract Amendment with RockSol Consulting Group.
Body
SUMMARY/KEY POINTS
* The Austin Roundabout project was originally planned to be completed by the end of December 2025.
* Staff found a gas line installed by Xcel Energy was too high and needs to be lowered; this required additional construction management support coordination.
* The contract amendment approved by Council for the streetlight installation will require additional construction management services.
* Town staff identified a grade issue prior to asphalt paving that required additional construction management services for the installation of a new inlet.
BACKGROUND OF SUBJECT MATTER:
May 13, 2025, Town Council approved a Construction Management Services General Services Agreement was awarded to RockSol Consulting Group Inc.
Oct. 28, 2025, Town Council approved an agreement with Xcel for the relocation of a gas line in the way of completing the Austin Avenue Roundabout.
Dec. 9, 2025, Town Council approved an amendment to the Construction contract with CEI for the installation of streetlights ...