SUBJECT:
Title
A Resolution of the Town Council of the Town of Erie Approving a Second Amendment to Agreement for Professional Services with Ulteig Operations, LLC for Construction Management Services for the Weld County Road 3 Bridge Replacement Improvements
Department
DEPARTMENT: Public Works
Presenter
PRESENTER(S): David Pasic, Public Works Director
Kieth Fiebig, Town Engineer
end
Time
TIME ESTIMATE: 0 minutes
end
For time estimate: please put 0 for Consent items.
Fiscal
FISCAL SUMMARY:
Cost as Recommended: $ 22,000
Balance Available: $ 111,029
Fund Capital Improvements Fund
Line Item Number: 110-70-425-605000-100085
New Appropriation Required: No
Policy
POLICY ISSUES:
The policy item here is whether to expend budgeted funds for the purpose of providing project management services for the grant funded bridge replacement.
Recommendation
STAFF RECOMMENDATION:
Approve the Resolution to amend the Agreement.
Body
SUMMARY/KEY POINTS
* This Second Amendment to Professional Services Agreement (PSA) will facilitate completion of consultant project management, inspection and documentation services needed to complete construction on schedule.
* The project is progressing toward Final Completion anticipated in late November 2025.
BACKGROUND OF SUBJECT MATTER:
The following prior items were authorized:
* On Nov. 12, 2024, the Town Council approved a PSA with Ulteig Operations to provide Construction Management Services to support construction for this project.
* On July 7, 2025, staff authorized the First Amendment to PSA to extend services through April 2025 to accommodate a schedule extension and inspect corrective construction work for impact attenuators, concrete transitions, bridge rails, and rip-rap installation; and review added traffic control and asphalt submittals.
The current resolution before the Council includes the Second Amendment to the PSA with Ulteig Operations for extended project ma...
Click here for full text