File #: 25-385    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 6/5/2025 In control: Town Council
On agenda: 7/8/2025 Final action:
Title: A Resolution of the Town Council of the Town of Erie Approving a Professional Services Agreement with Alfred Benesch & Co. for Construction Management of the Old Town - Colliers Hill Pedestrian Bridge Project
Attachments: 1. Resolution 25-111, 2. Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
SUBJECT:
Title
A Resolution of the Town Council of the Town of Erie Approving a Professional Services Agreement with Alfred Benesch & Co. for Construction Management of the Old Town - Colliers Hill Pedestrian Bridge Project

Department
DEPARTMENT: Public Works

Presenter
PRESENTER(S): David Pasic, Director of Public Works
Jonathan Williams, Civil Engineer
end

Time
Fiscal
FISCAL SUMMARY:
Cost as Recommended: $251,116
Balance Available: $4,800,000
Fund Urban Renewal Authority
Line Item Number: 800-90-871-605000-100215
New Appropriation Required: No

Policy
POLICY ISSUES:
The policy issue before Council is whether to or not to expend budgeted funds for the Construction Management Consulting Services for the Colliers Hill - Historic Downtown Erie Connection.

Recommendation
STAFF RECOMMENDATION:
Approve the Resolution

Body
SUMMARY/KEY POINTS
* The pedestrian bridge project connecting Colliers Hill to Historic Downtown Erie through Coal Creek Park has been in discussion for the past few years.
* The project is anticipated to last from August 2025 to April 2026.
* Benesch & Company will provide daily construction management, inspection services, bridge fabrication review, and oversee the structural conformance and erection of the ped bridge over Coal Creek on behalf of the Town of Erie.

BACKGROUND OF SUBJECT MATTER:
Earlier this year, Town staff solicited proposals for Construction Management Services to assist in providing adequate oversight for various on-going construction projects within the Town. Four firms were selected to provide the on-call services. Benesch & Company was identified as one of the four firms selected.

Staff contacted Benesch & Company to request a cost for construction oversight services based on the hourly rates identified in the Construction Management Services proposal. Staff coordinated with Benesch on the anticipated effort necessary for services. The work will include daily oversi...

Click here for full text