Skip to main content
Town of Erie
File #: 25-379    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 6/4/2025 In control: Town Council
On agenda: 7/8/2025 Final action:
Title: A Resolution of the Town Council of the Town of Erie Approving the First Amendment to the Construction Manager At-Risk (CMAR) Contract with ECI Site Construction Management, Inc. for the Schofield Farm Site Improvements Project
Attachments: 1. Resolution 25-127, 2. First Amendment to Construction Manager at Risk Contract Schofield Farm Open Space Site Improvements (PR-24-10), 3. Town of Erie Schofield Farm Open Space Improvements Construction Manager At Risk Contract (PR-24-10), 4. Schofield Farm Concept Design
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
SUBJECT:
Title
A Resolution of the Town Council of the Town of Erie Approving the First Amendment to the Construction Manager At-Risk (CMAR) Contract with ECI Site Construction Management, Inc. for the Schofield Farm Site Improvements Project

Department
DEPARTMENT: Parks & Recreation



Presenter
PRESENTER(S): Luke Bolinger, Director of Parks & Recreation
Kathy Kron, Development & Neighborhood Services Division Manager
end

Time
TIME ESTIMATE: 0 minutes
end

Fiscal
FISCAL SUMMARY:
Cost as Recommended: $3,807,804
Balance Available: $11,441,680
Fund Parks Improvement Impact Fund
Trails & Natural Areas Fund
LWCF Grant (Misc. Grants Capital Schofield Farm)
Tree Impact Fund
Line Item Number: 320-50-110-6-5000-100200 (PIIF)
210-50-110-605000-100200 (TNAF)
100-00-000-411300-100200 (LWCF Grant)
330-50-110-605000-100200 (TIF)

New Appropriation Required: No

Policy
POLICY ISSUES:
Per the Town's purchasing policy and current contract agreement with ECI Site Construction Management, the contract needs to be amended to move the project from the pre-construction services phase of the project to the construction phase. The amendment will incorporate the guaranteed maximum price (GMP) for Phase 2, Package A of the site improvements and allow staff to expend budgeted funds.

Recommendation
STAFF RECOMMENDATION:
Approve the Resolution to amend the Construction Manager At-Risk contract with ECI Site Construction Management, authorize the appropriate Town Officer to execute the agreement, and authorize staff to expend budgeted funds.

Body
SUMMARY/KEY POINTS
* Council approval is needed to amend the existing Construction Manager At-Risk (CMAR) Contract.
* Phase 2, Package A of the Site Improvements is ready to move from the design phase to the construction phase.
* Approving this contract amendment will allow construction to begin on the project.

BACKGROUND OF SUBJECT MATTER:
Town Council (then the...

Click here for full text