Town of Erie
File #: 23-277    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 5/9/2023 In control: Town Council
On agenda: 5/23/2023 Final action:
Title: A Resolution of the Board of Trustees of the Town of Erie Approving Change Order No. 3 with MPI Companies for the Street Maintenance Program
Attachments: 1. Resolution 23-061, 2. Change Order 3, 3. Construction Contract 06-28-2022, 4. Change Order 1, 5. Change Order 2
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: 

Title

A Resolution of the Board of Trustees of the Town of Erie Approving Change Order No. 3 with MPI Companies for the Street Maintenance Program

 

Body

 

DEPARTMENT:                                                                  Public Works

Department

 

PRESENTER(S):                                                                 Todd Fessenden, Public Works Director

First Name, Last Name, Title

 

FISCAL SUMMARY:

Cost as Recommended:                                          $ 284,615

Balance Available:                     $ 2,166,700

Budget Line Item Number:                      100-70-710-605000-100293

New Appropriation Required:                     No

 

POLICY ISSUES:

This matter concerns a change to a budgeted project and thus has minimal policy implications.

 

STAFF RECOMMENDATION:

Recommendation

Approve Change Order No. 3

 

End

 

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

In 2022, the Board of Trustees approved a construction contract with MPI Companies (Metro), to complete an overlay on a portion of Erie Parkway from County Line Road to Briggs Street, Phase 2 of the AirPark reconstruction project, and Change Order No. 1 for the Erie Parkway portion. Both pieces of the overall project are complete.

 

On Dec. 12, 2022, the Board approved Change Order No. 2 for reconstructing portions of Sheridan Boulevard in the amount of $2,342,445.55, with no contingency at that time due to funds available.

 

Change Order No. 3 is for redesigning the alignment of a segment on northbound Sheridan Parkway to provide a safer lane transition for vehicles. Redesign also includes a revised striping plan to remove inadequately sized on-street bike lanes and install a continuous striped median from Weld County Road 4 to Ridge View Drive. New signage will be installed to direct cyclists to the existing multi-use path along southbound Sheridan.

 

This change order is for $21,315. Additionally, we are requesting a contingency of $263,300 (approximately 10%) for any unforeseen items, for a total of $284,615.

 

Cost Summary

                     Change Order No. 2                     $2,342,445.55

                     Change Order No. 3                     $21,315.00

                     Subtotal                     $2,363,760.55

                     Contingency (~10%)                     $263,300.00

                     Total                     $2,627,060.55

 

BOARD PRIORITY(S) ADDRESSED: 

ü                     Attractive Community Amenities

ü                     Well-Maintained Transportation Infrastructure

ü                     Safe and Healthy Community

ü                     Fiscally Responsible

 

ATTACHMENT(S):                      

1.                     Resolution 23-061

2.                     Change Order 3

3.                     Original Construction Contract 06.28.2022

4.                     Change Order 1

5.                     Change Order 2