Town of Erie
File #: 22-311    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 8/5/2022 In control: Town Council
On agenda: 9/13/2022 Final action:
Title: A Resolution of the Board of Trustees of the Town of Erie Approving Change Order No. 2 to the Construction Contract with GoodLand Construction, Inc. for the Erie Parkway Reuse Waterline Improvements
Attachments: 1. Resolution 22-109, 2. Construction Contract, 3. Change Order 2
SUBJECT: Consent Agenda
Title
A Resolution of the Board of Trustees of the Town of Erie Approving Change Order No. 2 to the Construction Contract with GoodLand Construction, Inc. for the Erie Parkway Reuse Waterline Improvements
Body
DEPARTMENT: Public Works

PRESENTER/PREPARER: Todd Fessenden, Public Works Director
David Pasic, Town Engineer

TIME ESTIMATE:
only required for non-consent items

FISCAL SUMMARY:
Additional Budget as Recommended: $ 67,136
Balance Available (2022 funds): $260,173
Fund: Water
Budget Line Item Number: 500.70.110.605000.100374
New Appropriation Required: No

STAFF RECOMMENDATION:
Recommendation

Adopt the resolution approving the change order.

End
SUMMARY AND BACKGROUND OF SUBJECT MATTER:
At the September 28, 2021 Board Meeting the Board of Trustees awarded a construction contract to GoodLand Construction, Inc. (GoodLand), in the amount not to exceed $590,484 for the Erie Parkway Reuse Waterline; which includes the bid amount of $536,804, and a 10% contingency of $53,680.

The construction project attained Substantial Completion status and began the warranty period on June 29, 2022; one-month ahead of schedule. The Town and GoodLand worked well together in implementing traffic control along Erie Parkway between Powers Street and Briggs Street, that minimized traffic delays and promoted safety, eliminated night-construction and associated hazards, and minimized overnight lane closures. The contractor is currently working toward completing miscellaneous work items before final payment is approved by staff.

Staff requests approval of Change Order 2 in the amount of $105,867 to compensate GoodLand for actual costs incurred during construction and includes:

1. A reduction of $8,000 due to imported backfill not being used, which reduced cost;
2. An increase of $871 for actual installed aggregate base materials; and
3. An increase of $112,996 for actual "ton...

Click here for full text