Town of Erie
File #: 21-204    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 5/14/2021 In control: Town Council
On agenda: 6/8/2021 Final action:
Title: A Resolution of the Board of Trustees of the Town of Erie Approving an Agreement for Professional Services with RESPEC, Inc., for Construction Management Services for the Austin Avenue Water Main
Attachments: 1. Resolution, 2. Construction Management Contract, 3. Vicinity Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
SUBJECT: Consent Agenda
Title
A Resolution of the Board of Trustees of the Town of Erie Approving an Agreement for Professional Services with RESPEC, Inc., for Construction Management Services for the Austin Avenue Water Main

Body
DEPARTMENT: Public Works

PRESENTER/PREPARER: Todd Fessenden, Public Works Director
Wendi Palmer, Civil Engineer

FISCAL SUMMARY:
Cost as Recommended: $ 104,000
Balance Available (2021 Funds): $1,268,796 (with 1st Supplemental and 2020 rollover funds)
Fund: Water
Budget Line Item Number: 500-70-110-605000-100091
New Appropriation Required: No

STAFF RECOMMENDATION:
Recommendation
Approve the Resolution to award said contract, authorize the appropriate Town officer to execute said contract, authorize staff to expend budgeted funds.
End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:
The need for this new waterline connection was identified in the Town's Water Master Plan. The Erie Commons Development is in water pressure Zone 2. This area of Zone 2 is primarily served from pressure reducing vales (PRV's) from water pressure Zone 3. This connection will provide an additional direct connection to the Zone 2 water distribution system. Water feeding through the PRV's is pumped to Zone 3 then the pressure is reduced to feed Zone 2. This connection will allow water to be feed by gravity, reducing the volume of water pumped, which will provide a more reliable system with reduced energy costs. This project will also convert a Zone 2, 12-inch waterline on the west side of County Line Road north of Erie Parkway to Zone 3 which will provide a needed waterline for the Town Center development northwest of County Line Road and Erie Parkway.
At the June 9, 2020 Board Meeting the Board of Trustees approved a Change Order to an existing consultant agreement with RESPEC to redesign and prepare bid documents for the Austin Ave. Water Main project.
Now that the Austin Ave. Water Main project has bid, RESPEC...

Click here for full text