Town of Erie
File #: 20-237    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 4/17/2020 In control: Town Council
On agenda: 5/12/2020 Final action:
Title: A Resolution of the Board of Trustees of the Town of Erie Approving the Fourth Amendment to the Lynn R. Morgan Water Treatment Facility Expansion CMAR Contract With Garney Companies, Inc.
Sponsors: Public Works
Attachments: 1. Resolution, 2. CMAR 4th Amend.pdf
Related files: 20-075, 19-078, 19-587

SUBJECT: CONSENT

Title

A Resolution of the Board of Trustees of the Town of Erie Approving the Fourth Amendment to the Lynn R. Morgan Water Treatment Facility Expansion CMAR Contract With Garney Companies, Inc.

 

Body

DEPARTMENT:                                          Public Works

 

PRESENTER/PREPARER:                     Todd Fessenden, Public Works Director

                                                                                    Wendi Palmer, Civil Engineer

 

TIME ESTIMATE:

only required for non-consent items

 

FISCAL SUMMARY:

Cost as Recommended:                                          $1,848,281

Balance Available:                                                               $   629,747

                                                                                                         $1,515,304

Fund:                                                                                                         Water

Budget Line Item Number:                      500-70-110-605000-100258(with supplemental appropriation)

                     500-70-110-605000-100305(with supplemental appropriation)

New Appropriation Required:                     No

 

STAFF RECOMMENDATION:

Recommendation

Approve the Resolution to amend said agreement, authorizing the appropriate Town officer to execute said agreement and authorize staff to expend budgeted funds.

 

End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

Background:

The 2020 Water Fund Budget has funds appropriated for constructing the Water Treatment Plant Expansion and for the construction of a Hydroelectric (turbine) Facility at the Water Treatment Plant. This turbine is anticipated to supply 20% of the existing plant power demand, and the power generation will increase as the Town grows.

 

During the design of the Water Treatment Plant Expansion project, the Town had the opportunity to perform a feasibility study, with partial grant funding from Colorado Water Resources and Power Development Authority in the amount of $15,000, for a hydroelectric facility at the water treatment plant.  The Feasibility Study was presented to the Board at the August 27, 2019 Board of Trustees meeting at which time a professional services agreement was approved for Burns & McDonnel to design the hydroelectric facility. Staff informed the Board of Trustees we intended to bring to the Board an amendment to the CMAR contract for the construction of the hydroelectric facility; potentially contingent upon obtaining additional grant funding for the project.

 

Burns & McDonnel has worked with Garney Construction reviewing the 60% plans for constructability.  With the completion of the 90% plans, Garney has provided a guaranteed maximum price of $1,848,281 for the construction of the Hydroelectric Facility. With the approval of the Fourth Amendment to the CMAR Contract, Garney will bid sub-contractors and suppliers to ensure competition and the best price for the project. 

 

Town Staff with the assistance of Burns & McDonnell submitted an application to the Department of Local Affairs (DOLA) for a Renewable and Clean Energy Grant in the amount of $766,704. The Board approved a resolution at the December 10, 2019 Board meeting authorizing the application for funding. If the Town does not fund this project, the Clean Energy Grant would need to be returned to DOLA, this could jeopardize future funding opportunities from DOLA. Worth noting is the Town also received a $750,000 grant from a similar DOLA grant program for the next phase of our Community Park.

 

Construction Manager at Risk (CMAR) Amendment history:

 

                     At the February 26, 2019 Board Meeting, the Board approved Amendment 1 to the CMAR Contract with Garney, which allowed for the early procurement of membranes.

 

                     At the May 14, 2019 Board Meeting, the Board approved Amendment 2 to the CMAR Contract with Garney for authorization for the Guaranteed Maximum Price (GMP) for the Water Treatment Plant Expansion.

 

                     At the January 28, 2020 Board Meeting, the Board approved Amendment 3 to the CMAR Contract with Garney for authorization to extend the Zone 3 Waterline beyond the southerly property line of the water treatment plant to a location south of Marfell Street.

 

In addition to this resolution, on the agenda tonight is a resolution to approve a change order to Burns & McDonnell’s Professional Services Agreement for providing construction administration for the hydroelectric facility project (20-238).  Burns & McDonnell’s expertise is needed for oversight of the construction of the hydroelectric facility.

 

Original Water Treatment Plant Expansion Project Schedule

                     Notice of Award                                                               May 15, 2019

                     Notice to Proceed                                                               May 22, 2019

                     Membrane Complete                                          April, 2020

                     Construction Complete                                          September, 2020

 

Hydroelectric Facility Schedule

                     Amendment 4 approval                                          May 12, 2020

                     CMAR bid Subs & Suppliers                     June, 2020

                     Structure Complete                                                               December, 2020

                     Install Turbine                                                                 Spring, 2021

 

Fiscal Impact:

The Water Treatment Plant Expansion Project is approximately 70% complete.  At this point in the CMAR project the contractor is projecting a $600,000 savings due to an efficient and well run project. Although at this point the $600,000 is still encumbered, when the project closes out, the savings will be returned to the Water Fund. The costs below do not take into account this potential savings.

 

Project Construction Cost

                     Preconstruction Phase Services                                                               $       24,210

                     Amendment 1 (19-078)                                                                                    $  2,011,057

                     Amendment 2 (19-222)                                                                                    $  8,750,768

                     Amendment 3 (20-075)                                                                                    $     184,915

                     Amendment 4 (20-237)*                                                                                    $   1,848,281

                     Total Cost for CMAR                                                                                    $12,819,231

 

Project Design and Administrative Costs

Water Plant Expansion

Design Services (18-187)                                                                                    $     459,116

                     Design Services Contingency (18-187)                                          $       65,884

                     Construction Administration (19-223)                                          $      806,722

                     Hydro Design (19-292)*                                                                                    $      134,726

                     Hydro Construction Admin (20-238)*                                          $      166,158

                     Total Cost Design & Administration                                          $    1,632,606

 

Total Project Cost                                                                                                                              $  14,451,837

 

Costs for the Hydroelectric Facility are designated with an *

 

                     Engineering Costs                                                                                                         $   300,884

                     Construction Costs                                                                                                         $1,848,281

                     Total Cost for Hydroelectric Facility                                          $2,149,165

 

                     Funding sources for Hydroelectric Facility

                     DOLA Grant                                                                                                                              $   766,704

                     Feasibility Study Grant                                                                                    $     15,000

                     Water Fund                                                                                                                              $1,367,461

                     Total funding for Hydroelectric Facility                     $2,149,165                                          

 

 

ATTACHMENTS:                      

 

1.                     Resolution

2.                     Amendment No. 4 CMAR Contract