File #: 20-151    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 2/27/2020 In control: Town Council
On agenda: 3/10/2020 Final action:
Title: A Resolution of the Board of Trustees of the Town of Erie Approving Change Order No. 2 to the Agreement with Leonard Rice Engineers for the Water Supply Planning Project in the Amount of $50,000
Attachments: 1. Resolution, 2. Change Order
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
SUBJECT: CONSENT
Title
A Resolution of the Board of Trustees of the Town of Erie Approving Change Order No. 2 to the Agreement with Leonard Rice Engineers for the Water Supply Planning Project in the Amount of $50,000

Body
DEPARTMENT: Public Works

PRESENTER: Todd Fessenden, Public Works Director

FISCAL SUMMARY:
Cost as Recommended: $50,000
Balance Available: $1,110,026
Budget Line Item Number: 500-70-110-605000-100290
New Appropriation Required: No

STAFF RECOMMENDATION:
Recommendation
Approve the resolution to execute said change order, authorize the appropriate Town officer to execute said change order, and authorize staff to expend budgeted funds.

End
SUMMARY AND BACKGROUND OF SUBJECT MATTER:
Background:
The Town has an existing contract with Leonard Rice Engineers to assist in exploring the development of groundwater wells adjacent to Boulder Creek near the North Water Reclamation Facility, which will be a significant and redundant water source for the Town. As this project grew from a conceptual phase to a viable project and Water Court filing the Town requested that Leonard Rice perform additional engineering support in developing information required as part of the Water Court filing, related to the water rights that would be needed to develop the well field. Ongoing planning and project development will also be covered through this change order. Paul Zilis, Town Water Counsel has also reviewed this scope and supports the need for this change order. Funds are budgeted for this work

Next phase of this project will include design of a well field and associated pipes and pumps, acquisition of property and permitting. A new Scope of Work is being developed for that phase of work and we will be bringing that before the Board in the near future.

Fiscal Impact:

To date the town has expended roughly $140,000 on this effort with Leonard Rice Engineers, Inc.to date. If this well field produces the anticipated volume of water the cost of this supply wi...