Town of Erie
File #: 19-314    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 6/28/2019 In control: Town Council
On agenda: 7/9/2019 Final action:
Title: A Resolution of the Board of Trustees of the Town of Erie Approving an Agreement for Services with Haynes Mechanical Systems for the Erie Community Center HVAC Repairs in the amount of $30,900
Attachments: 1. Resolution, 2. General Services Agreement – ECC HVAC RTU 4
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: CONSENT AGENDA

Title

A Resolution of the Board of Trustees of the Town of Erie Approving an Agreement for Services with Haynes Mechanical Systems for the Erie Community Center HVAC Repairs in the amount of $30,900

Body

 

DEPARTMENT:                                          Public Works

 

PRESENTER:                                                               Todd Fessenden, Public Works Director

 

FISCAL INFORMATION:

Cost as Recommended:                                          $30,900

Balance Available:                                                               $0

Budget Line Item Number:                                           100-70-440-522100

New Appropriation Required:                     Yes

 

STAFF RECOMMENDATION:

Recommendation

Approve the resolution to approve said agreement, authorizing the appropriate Town Officer to execute said agreement, and authorize staff to expend funds.

End

 

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

The Erie Community Center roof top HVAC unit that supplies heating and cooling to the pool area is nearing the end of its service life. This unit was proposed to be replaced in 2020 budget with two units to ensure redundancy. Recently the compressors in the existing unit failed. It can still exhaust air and introduce fresh air, but without functioning compressors the humidity will not be controlled.

 

The Town received a quote from our current contractor, Haynes Mechanical, to replace the compressors and ensure a comfortable environment for recreation center patrons. The total cost of the repair is $30,900. Staff has already placed the order for the parts, which was just under $25,000 and within the Town Administrator’s authority to approve. We anticipate these repairs will be complete by mid-July.

 

ATTACHMENTS:                      

a.                     Resolution

b.                     General Services Agreement - ECC HVAC RTU 4