Town of Erie
File #: 18-378    Version: 1 Name:
Type: Consent Agenda Status: Passed
File created: 10/12/2018 In control: Town Council
On agenda: 10/23/2018 Final action: 10/23/2018
Title: A Resolution Of The Board Of Trustees Of The Town Of Erie Approving A Payment To United Power For Relocation And Providing Electrical Power And Lighting For The Erie Parkway Bridge Over Coal Creek In The Amount Of $70,158.93 And A Contingency Of $7,016.07
Sponsors: Public Works
Attachments: 1. Erie Parkway Bridge over Coal Creek Vicinity Map.pdf, 2. Resolution 18-378, 3. Cost Estimate
Related files: 20-057

SUBJECT:

Title

A Resolution Of The Board Of Trustees Of The Town Of Erie Approving A Payment To United Power For Relocation And Providing Electrical Power And Lighting For The Erie Parkway Bridge Over Coal Creek In The Amount Of $70,158.93 And A Contingency Of $7,016.07.Body

DEPARTMENT:                                                               Planning and Development

 

PRESENTER/PREPARER:                     Todd Bjerkaas, Director of Planning and Development

Russell Pennington, Town Engineer

                                                                                                         Wendi Palmer, Civil Engineer

 

FISCAL INFORMATION:

Cost as Recommended:                                          $ 77,175

Balance Available:                                                               $ 9,182,769 (with 2nd 2018 Supplemental and 2019 Budget)

Fund:                                                                                                         Transportation Impact

Budget Line Item Number:                                           300-70-110-605000-100216

New Appropriation Required:                     No

 

STAFF RECOMMENDATION:

Recommendation

Approve the Resolution for payment to United Power, authorize Staff to expend funds and contingency funds.

End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

 

At the June 13, 2017 Board Meeting the Board of Trustees awarded the design contract for the Erie Parkway Bridge Over Coal Creek to RockSol Consulting Group, Inc. At that time the Board of Trustees was notified that Staff will bring contracts back to the Board for the construction of this project.

 

During the design of the bridge it was determined that the existing United Power electrical line would need to be relocated.  This line is in an easement so the Town will be responsible for the cost to relocate it.  In addition to the relocation cost, new street lights are needed and power for Town owned lights on the bridge.

 

In addition to this resolution, on the agenda tonight is a resolution for approving a Construct Contract for the construction of the Erie Parkway Bridge Over Coal Creek (Consent Agenda 18-375) and resolution for approving a Construct Management Contract for the construction of the Erie Parkway Bridge Over Coal Creek (Consent Agenda 18-376).

 

Staff is recommending paying the cost estimate of $70,158.93 to United Power.

 

In addition to the United Power Costs, there will be construction and construction management costs.

 

 

Cost Summary

United Power Payment                                                                                    $    70,158.93

                     Contingency                      (10%)                                                                                                         $      7,016.07

                     Total                                                                                                                                                   $    77,175.00

 

Consent Agenda 18-375

Construction Contract                                                               $    5,124,696.75

                     Contingency                      (10%)                                                                                    $       512,503.25

                     Total                                                                                                                              $    5,637,200.00

 

Consent Agenda 18-376

Construction Management Contract                                          $    484,834

                     Contingency                      (10%)                                                                                                         $      48,466

                     Total                                                                                                                                                   $    533,300

 

Total Project Cost                                                                                                                              $    6,247,675                     

 

Project Budget

The 2018 Transportation Impact Budget has $2,182,769 remaining for the Erie Parkway Bridge over Coal Creek after the second supplemental.  There is $7,000,000 in the 2019 Transportation Impact budget for the Erie Parkway Bridge over Coal Creek.  The anticipated expenses for 2018 will be less than $2,000,000.

 

Project Schedule

                     Notice of Award                                                               October 24, 2018                                          

                     Notice to Proceed                                                                November 7, 2018

                     Construction Complete                                                    Fall 2019

 