Title: A Resolution Of The Board Of Trustees Of The Town Of Erie Authorizing A Consulting Agreement With Merrick & Company For The Construction Management Of The Erie Parkway 30" Waterline Relocation Project In The Amount Of $55,612 For Construction And $5,588 For Contingency.
Attachments: 1. Vicinity Map for Erie Parkway 30-inch Waterline Relocation.pdf, 2. CONSULTING AGREEMENT.pdf, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: CONSENT AGENDA

Title

A Resolution Of The Board Of Trustees Of The Town Of Erie Authorizing A Consulting Agreement With Merrick & Company For The Construction Management Of The Erie Parkway 30” Waterline Relocation Project In The Amount Of $55,612 For Construction And $5,588 For Contingency.

Body

DEPARTMENT:                                                               Planning and Development

 

PRESENTER/PREPARER:                     Todd Bjerkaas, Planning and Development Director

                                                                                                         Russell Pennington, Town Engineer                                                                                                                                                                        Wendi Palmer, Civil Engineer

FISCAL INFORMATION:

Cost as Recommended:                                          $   61,200

Balance Available                                                               $ 139,700

Fund:                                                                                                         Water

Budget Line Item Number:                                           500-70-110-605000-100286

New Appropriation Required:                     No (With 300,000 budget line transfer from 500-70-110-605000-100260)

 

STAFF RECOMMENDATION:

Recommendation

Approve the Resolution to award said contract, authorize the appropriate Town officer to execute said contract, authorize Staff to expend contracted funds and contingency funds.

End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

 

During the design of the Erie Parkway Bridge over Coal Creek, it was determined that the 30-inch waterline will need to be relocated due to conflicts with the bridge improvements.  During the First 2018 Supplemental budget, funds were approved for relocating this line.  The Design was completed by Merrick & Company who has worked on multiple other projects for the Town.

 

Merrick & Company was asked to provide a cost for construction management.  The construction management services will include inspection, documentation and oversight during construction. Geotechnical testing services will be provided by the Erie Parkway Bridge Designer (RockSol).  The Town’s construction inspectors are focused on construction inspection and oversight of residential and commercial development. Due to the complexity of this project, Staff believes it is in the Town’s best interest to have the design firm provide construction management services.

 

Staff is recommending awarding a consulting agreement for construction management services for the Erie Parkway 30” Waterline Relocation Project to Merrick & Company, in the amount of $55,612 with a contingency amount of $5,588.

 

Cost Summary

                     Construction Management Contract                     $      55,612

                     Contingency                      (10%)                                                                                    $        5,588

                     Total                                                                                                                              $      61,200

 

Consent Agenda 18-298 Awarded at the 8-28-18 BOT Meeting

                     Construction Contract                                                               $    528,240

                     Contingency                      (25%)                                                                                    $    132,060

                     Total                                                                                                                              $    660,300

 

Other Project Costs

                     Design                                                                                                         $      25,000

Compaction Testing                                                                                    $        5,000

                     Total                                                                                                                              $      30,000

 

Total Project Cost                                                                                                         $    721,530

 

Project Schedule

                     Notice to Proceed                                                                September 12, 2018

                     Construction Complete                                                    December 2018

 