Town of Erie
File #: 18-297    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 8/16/2018 In control: Town Council
On agenda: 8/28/2018 Final action:
Title: A Resolution Of The Board Of Trustees Of The Town Of Erie Authorizing A Construction Contract And Executing Supplemental Agreement No. 1 With PV Consulting, Inc. For The Federal Aviation Administration Grant AIP Project No. 3-08-0090-018-2018 For The Construction Of A Snow Removal Equipment Building In The Amount Of $595,107.00 For Construction And $45,000 For Contingency.
Attachments: 1. Resolution, 2. 2rev1 166371 Construction Agreement, 3. Supp Agreement #1_rev082218_signed
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: Consent

Title

A Resolution Of The Board Of Trustees Of The Town Of Erie Authorizing A Construction Contract And Executing Supplemental Agreement No. 1 With PV Consulting, Inc. For The Federal Aviation Administration Grant AIP Project No. 3-08-0090-018-2018 For The Construction Of A Snow Removal Equipment Building In The Amount Of $595,107.00 For Construction And $45,000 For Contingency.

Body

DEPARTMENT:                                                                Planning and Development

 

PRESENTER:                                                               Russell W Pennington, Town Engineer

                                                                                                         Jason Hurd, Airport Manager

 

FISCAL INFORMATION:

Cost as Recommended:                                          $ 640,107

Balance Available:                                                               $ 512,300

Fund:                                                                                                         Airport

Budget Line Item Number:                                           530.70.110.605000.100168

New Appropriation Required:                     Yes (A new FAA Grant is being accepted tonight in the   amount of $616,039)

 

STAFF RECOMMENDATION:

Recommendation

 

Approve Resolution awarding said contract, authorizing the Mayor to execute said contract, authorizing Staff to expend contracted funds and contingency funds.

 

End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

 

Each year, the FAA dedicates $150,000 in General Aviation (GA) Funds to the Erie Municipal Airport for FAA approved projects.  These funds comprise 90% of the project funding with the remaining 10% split between the Colorado Division of Aeronautics and the Town.

 

The 2018 Operating Budget includes a project to construct a Snow Removal Equipment Building (SRE) at the Erie Municipal Airport and using GA Funds that have been saved up for a few years. 

 

A great deal of effort was put forth to attract bidders to this project. A total of nine (9) contractors with a local presence were approached to identify interest in the project. Those expressing interest were provided with the Invitation for Bids. Additionally, the advertisement for bids for the project was published for three (3) consecutive weeks in the Daily Camera newspaper prior to the bid opening. A pre-bid conference was subsequently held onsite on July 25, 2018 to answer questions and show the project to potential bidders. This meeting was well attended (two potential Prime Bidders who had already picked up Plans at that time and three potential Prime Bidders who had yet to pick up Plans).

 

Bids were received for the above noted project on August 1, 2018, and one (1) bid was received as summarized in the attached bid tabulation.

Because there was only one bid received, and the bid was in excess of the Engineer’s Estimate of Construction Cost, Staff entered into discussions with PV Consulting, Inc. to negotiate scope/price reductions for the proposed project.  Value Engineering cost savings were achieved and the new Schedule I construction cost is $595,107.

 

Due to the bid being in excess of the Engineer’s Estimate and the current budget allowed, the FAA has allowed the Town to borrow from next year’s GA Fund.  With this increase in FAA funding, the Town’s match has only increased by $10,091.  CDOA is still providing $25,908 towards the project.  The budget changes will be included in the next supplemental appropriation process.

 

Therefore, Staff’s recommendation is to award Schedule I to PV Consulting, Inc. for a total contract amount of $595,107 contingent upon receiving both concurrence of award and the associated grant offer from the FAA.

 

The following budget needs to be developed for AIP No. 3-08-0090-018-2018 consisting of:

Schedule I: Construct Snow Removal Equipment Building

 

 

DESCRIPTION

AMOUNT

 Construction

Schedule I

$595,107.00

 

 

Construction Total

$595,107.00

 Engineering

Design Engineering

$19,832.00

Construction Engineering

$28,769.00

Engineering Total

$48,601.00

 Administration

Admin Expenses (Estimated)

$2,000.00

Utility Extension Costs (Fronted by Erie)

$1,000.00

 

Administration Total

$3,000.00

 Total Project Cost

 $646,708.00

  Budget Summary

FAA Share 90.00%

$582,037

State Share 3.8%

$  25,908

Local Share 6.2%

$  38,763

 

 

 

 

 

 

Recommendation

Staff recommends award of contract to PV Consulting, Inc.  PV Consulting, Inc is familiar with this type of work and the Town’s consultant has worked with PV Consulting on other similar airport projects. 

 

 

Project Schedule  

                     Notice of Award                     August, 2018

                     Notice to Proceed                     September, 2018

                     Estimated Project Completion                     Spring, 2019

 

 

ATTACHMENTS:

a.                     Construction Agreement

b.                     Supplemental Agreement No. 1

c.                     Resolution