Town of Erie
File #: 18-245    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 7/13/2018 In control: Town Council
On agenda: 8/14/2018 Final action:
Title: A Resolution Authorizing Award Of Construction Contract To W.L. Contractors, Inc. For The In-Traffic Signal Cabinet Upgrades Project In The Amount Of $60,490.00 And Contingency In The Amount Of $6,010 And Setting Forth Details In Relation Thereto.
Attachments: 1. Traffic Signal Cabinet Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: CONSENT AGENDA

Title

A Resolution Authorizing Award Of Construction Contract To W.L. Contractors, Inc. For The In-Traffic Signal Cabinet Upgrades Project In The Amount Of $60,490.00 And Contingency In The Amount Of $6,010 And Setting Forth Details In Relation Thereto.

 

Body

DEPARTMENT:                                          Public Works

 

PRESENTER:                                                                                    Todd Fessenden, Public Works Director

 

FISCAL INFORMATION:

Cost as Recommended:                                          $ 70,000

Balance Available:                                                               $ 70,000

Budget Line Item Number:                                           100-70-710-605000-100251

New Appropriation Required:                                          No

 

STAFF RECOMMENDATION:

Recommendation

Approve Resolution awarding said contract, authorizing the Mayor to execute said contract, authorizing Staff to expend contracted funds and contingency funds.

 

End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

The 2018 Capital Budget includes funds for the installation of new signal heads at the existing traffic signals located at Erie Parkway/Flatiron Meadows Boulevard, Erie Parkway/Colliers Parkway, Erie Parkway/Meller Street, Erie Parkway and Weld County Road 5, and County Line Road/Austin Avenue.

 

The Town installed these permissive left turn signals last year on Erie Parkway at Briggs and Powers Streets based on an evaluation that was completed on the traffic movements at these intersections.  From that evaluation, a new traffic signal head with a dedicated left turn signal was installed at both intersections for traffic turning off of Erie Parkway. Along with the new signal heads, new controllers were installed to better manage the signals functions.

 

A total cost was requested from W.L. Contractors who is the current the Town’s traffic signal and school speed awareness maintenance services contractor. The proposed costs include traffic control equipment and installation.

 

Project Summary  

                     Contract                     $60,490

                     Contingency                     $9,510

                     Total                     $70,000

 

 

 

 

Project Schedule  

                     Notice of Award                     August, 2018

                     Notice to Proceed                     August, 2018

                     Estimated Project Completion                     November, 2018

 

Recommendation

Staff has reviewed the bid and found the bid to be competitive.  Staff recommends award of contract to W.L. Contractors, Inc.  WL is familiar with this type of work and has completed successful projects for the Town of Erie as well as other municipalities.

 

ATTACHMENTS:                      

a.                     Resolution