SUBJECT:  STAFF REPORT

Title

 

WCR 6 Road Closure

 

Body

DEPARTMENT:                     Public Works

 

PRESENTER:                     Russell Pennington, Deputy Director of Public Works

                                                               Matt Wiederspahn, P.E., Development Engineer

 

FISCAL INFORMATION:

Cost as Recommended:                                          N/A

Balance Available:                                          N/A

Budget Line Item Number:                     N/A

New Appropriation Required:                     N/A                                                                                                                              

 

STAFF RECOMMENDATION:                     None

Recommendation

 

End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

 

Crestone Energy is currently constructing an Oil and Gas Gathering Facility in Weld County on the northwest corner of WCR 6 and WCR 7, with both roads being within Town Limits.  As part of the project they are constructing a 12 inch water line in WCR 6 as well as paving the road for a half mile west of WCR 7.  WCR 6 is currently a low maintenance dirt road with minimal daily traffic.   

The contractor is proposing to start the closure on June 14th with a targeted re-opening of the beginning of August, weather permitting.  The Town will send out a press release and the contractor will install message boards notifying drivers of the closure.

ATTACHMENTS:                      

A.                     Detour Map