Title: Consideration Of A Resolution Authorizing Award Of A Construction Contract To Metro Pavers For Improvements To Portions Of Vista Parkway In The Amount Of $72,008.62 and a contingency amount of $7,991.38.
Attachments: 1. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: CONSENT AGENDA

Title

Consideration Of A Resolution Authorizing Award Of A Construction Contract To Metro Pavers For Improvements To Portions Of Vista Parkway In The Amount Of $72,008.62 and a contingency amount of $7,991.38. 

Body

 

DEPARTMENT:                                                               Public Works

 

PRESENTER/PREPARER:                     Russell Pennington, Deputy Director of Public Works

                                                                                                         Jody Lambert, Operations and Maintenance Manager

 

FISCAL INFORMATION:

Cost as Recommended:                                          $ 80,000

Balance Available:                                                               $ 80,000

Fund:                                                                                                         General Fund

Budget Line Item Number:                                           100-70-710-605000-100235

New Appropriation Required:                                          No

 

STAFF RECOMMENDATION: Approving the Resolution to award said contract, authorizing the appropriate Town officer to execute said contract, authorizing Staff to expend contracted funds and contingency funds.

Recommendation

 

End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

The 2017 General Fund Budget includes money to repair a few locations on Vista Parkway.  Vista Parkway was evaluated from County Line Road to State Highway 7 regarding structure integrity and ride ability. From that evaluation, four areas between Parkdale Circle to Mountain View Boulevard was selected to make ride ability improvements in 2017. Staff requested a proposal from the Metro Pavers, who is under contract for asphalt services. The costs are:

 

Locations                                                                                           Estimated Cost

Location 1 (Near Hickory Drive)                                          $22,844.62

Location 2 (Near Single Tree Lane)                                           $14,531.60

Location 3 (Near Driver Lane)                                            $22,745.30

Location 4 (Between Parkdale Circle & Driver Lane)                                           $11,887.10

Total                                          $72,008.62

 

Staff recommends awarding the construction contract to Metro Pavers for improvements to portions of Vista Parkway, in the amount of $72,008.62.

 

Cost Summary:

Contract                     $72,008.62

Contingency                     $7,991.38

Total                     $80,000.00

 

 

 

Schedule:

                     Notice of Award                                                               June 14, 2017                                          

                     Notice to Proceed                                                                June 28, 2017

                     Construction Complete                                                    Fall 2017

 

ATTACHMENTS:                      

a.                     Resolution