Town of Erie
File #: 17-220    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 5/10/2017 In control: Town Council
On agenda: 6/13/2017 Final action:
Title: Consideration of A Resolution Authorizing Award of a Construction Contract To Scott Contracting, Inc., For the Zone 3 Waterline Extension Phase 1 In The Amount of $1,650,089.70 for Construction and $249,910.30 for Contingency.
Attachments: 1. Work Area and Staging Exhibit.pdf, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: CONSENT AGENDA

Title

Consideration of A Resolution Authorizing Award of a Construction Contract To Scott Contracting, Inc., For the Zone 3 Waterline Extension Phase 1 In The Amount of $1,650,089.70 for Construction and $249,910.30 for Contingency.

Body

DEPARTMENT:                                                               Public Works

 

PRESENTER/PREPARER:                     Russell Pennington, Deputy Public Works Director

                                                                                                         Wendi Palmer, Civil Engineer

 

FISCAL INFORMATION:

Cost as Recommended:                                          $ 1,900,000.00

Balance Available:                                                               $ 2,168,800 (Pending first 2017 supplemental and 2016 funds to be rolled-over)

Fund:                                                                                                         Water

Budget Line Item Number:                                           500-70-110-605000-100135

New Appropriation Required:                                          No

 

STAFF RECOMMENDATION:

Recommendation

Approve the Resolution to award said contract, authorize the appropriate Town officer to execute said contract, authorize Staff to expend contracted funds and contingency funds.

End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

 

The Town Board previously awarded the Design for the Zone 3 Waterline Extension Phase 1 to JR Engineering At the September 22, 2015 Board Meeting. The Town Board also authorized the purchase of a permanent utility easement and temporary construction easement for the construction of this project at the March 28, 2017 Board Meeting. Also before you tonight is a Construct Management Contract for the Zone 3 Waterline Extension Phase 1 (Consent Agenda 17-219).

In an effort to ensure that qualified contractors bid this project, Town Staff solicited pipeline contractors to submit pre-qualification statements demonstrating their capabilities.  Fourteen contractors were pre-qualified to bid on this project.  The Pre-qualified contractors were provided bid documents on April 18, 2017.  

 

 

 

 

 

The following bids were received on May 25, 2017:

 

Bid Information:

Contractor                                                                                                                              Bid Amount                                          

Scott Contracting, Inc.                                                                                    $   1,650,089.70                                          

ESCO Construction Co.                                                                                    $   1,662,729.60                                          

Duran Excavating, Inc.                                                                                    $   1,824,065.00                                          

Concrete Works of Colorado, Inc.                                                               $   1,975,670.00                                          

Iron Woman Construction, Inc.                                                               $   2,052,817.00                                          

 

Engineer’s Estimate                                                                                                         $   1,938,330.00                     

 

The low bidder is Scott Contracting, Inc.  Scott Contracting has been in business in Colorado for 22 years.  Similar sized projects they have completed in include: 104th Ave Improvements for Commerce City, Raw Water project for Cottonwood Water and Sanitation District, Waterline project for City of Aurora, and a Waterline project for Arapahoe County Water and Wastewater Authority.  

 

In addition to these similarly sized projects, Scott Contracting, Inc. has completed projects for CDOT, Park Creek Metro District & Denver Water, and are currently completing projects for Shea Homes, Crystal Valley Metro, KB Home, LGI Homes Group, Flatiron Construction and Lennar.

 

Staff is recommending awarding the construction contract for the Zone 3 Waterline Extension Phase 1 to Scott Contracting, Inc., in the amount of $1,650,089.70.

 

Cost Summary

                     Construction Contract                                                               $    1,650,089.70

                     Contingency                      (15%)                                                                                    $       249,910.30

                     Total                                                                                                                              $    1,900,000.00

 

                     Consent Agenda 17-219

Construction Management Contract                                          $    75,484

                     Contingency                      (20%)                                                                                                         $    15,116

                     Total                                                                                                                                                   $    90,600

 

Total Project Cost                                                                                                         $    1,990,600.00                     

 

Project Schedule

                     Notice of Award                                                               June 14, 2017                                          

                     Notice to Proceed                                                                June 28, 2017

                     Construction Complete                                                    Fall 2017

 

ATTACHMENTS:                      

 

a.                     Vicinity Map

b.                     Resolution