File #: 17-219    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 5/10/2017 In control: Town Council
On agenda: 6/13/2017 Final action:
Title: Consideration of A Resolution Authorizing Award of a Construction Management Contract To JR Engineering, LLC, For the Zone 3 Waterline Extension Phase 1 In The Amount of $75,484 for Construction Management and $15,116 for Contingency.
Attachments: 1. Work Area and Staging Exhibit.pdf, 2. Zone 3 Waterline Extension Construction Management Consulting Agreement.pdf, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: CONSENT AGENDA

Title

Consideration of A Resolution Authorizing Award of a Construction Management Contract To JR Engineering, LLC, For the Zone 3 Waterline Extension Phase 1 In The Amount of $75,484 for Construction Management and $15,116 for Contingency.

Body

 

DEPARTMENT:                                                               Public Works

 

PRESENTER/PREPARER:                     Russell Pennington, Deputy Public Works Director

                                                                                                         Wendi Palmer, Civil Engineer

 

FISCAL INFORMATION:

Cost as Recommended:                                          $ 90,600.00

Balance Available:                                                               $ 2,168,800 (Pending first 2017 supplemental and 2016 funds to be rolled-over)

Fund:                                                                                                         Water

Budget Line Item Number:                                           500-70-110-605000-100135

New Appropriation Required:                     No

 

STAFF RECOMMENDATION:

Recommendation

Approve the Resolution to award said contract, authorize the appropriate Town officer to execute said contract, authorize Staff to expend contracted funds and contingency funds.

End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

 

The Town Board previously awarded the Design for the Zone 3 Waterline Extension Phase 1 to JR Engineering At the September 22, 2015 Board Meeting. The Town Board also authorized the purchase of a permanent utility easement and temporary construction easement for the construction of this project at the March 28, 2017 Board Meeting. Also before you tonight is a Construct Contract for the construction of the Zone 3 Waterline Extension Phase 1 (Consent Agenda 17-220).

 

Now that the project has bid, JR Engineering LLC. was asked to provide a cost for construction management.  The construction management services will include Inspection, documentation and oversight during construction and geotechnical testing services.  The Town’s construction inspectors are focused on construction inspection and oversight of residential and commercial development. Due to the location and complexity of this project, Staff believes it is in the Town’s best interest to have the design firm provide construction management services.

 

Staff is recommending awarding the construction management contract for the Zone 3 Waterline Extension Phase 1 to JR Engineering LLC, in the amount of $75,484.

 

Cost Summary

                     Construction Management Contract                                          $        75,484.00

                     Contingency                      (20%)                                                                                                         $        15,116.00

                     Total                                                                                                                                                   $        90,600.00

 

Consent Agenda 17-220

                     Construction Contract                                                                                    $    1,650,089.70

                     Contingency                      (15%)                                                                                                         $       249,910.30

                     Total                                                                                                                                                   $    1,900,000.00

 

Total Project Cost                                                                                                                              $    1,990,600.00                                                                                    

 

 

Project Schedule

                     Notice of Award                                                               June 14, 2017                                          

                     Construction Complete                                                    Fall 2017

 

ATTACHMENTS:                      

 

a.                     Vicinity Map

b.                     Consultant Agreement

c.                     Resolution