Town of Erie
File #: 17-154    Version: 1 Name:
Type: General Business Status: Agenda Ready
File created: 4/10/2017 In control: Town Council
On agenda: 4/25/2017 Final action:
Title: Star Meadows Park Construction
Sponsors: Parks & Recreation, Farrell Buller
Attachments: 1. Star Meadows Park Master Plan Renderings, 2. Goodland Construction, Inc, Corrected Bid

SUBJECT:  General Business

Title

 

Star Meadows Park Construction

 

Body

DEPARTMENT:  Parks & Recreation

 

PRESENTER:  Farrell Buller, Parks & Recreation Director

 

FISCAL INFORMATION:

Cost as Recommended:  $ 2,338,325.45

Balance Available:  $ 1,600,000.00 (Parks Improvement Impact Fund)

                                                $       0.00 (Tree Impact Fund)

Budget Line Item Number:  320-50-110-605000-100193

                                                                    330-50-110-605000-100193

New Appropriation Required:  Yes - Parks Improvement Impact Fund $ 690,000.00

                                                                         Yes - Tree Impact Fund $ 48,350.00                     

 

STAFF RECOMMENDATION:

Recommendation

 

Approve Goodland Construction, Inc. to serve as general contractor and Design Concepts to serve as construction administrator

 

End

 

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

 

In the fall of 2016 the Board of Trustees approved the site master plan for the Flatiron Meadows Neighborhood Park (Star Meadows Park) and authorized the Parks & Recreation Department to contract with Design Concepts to complete construction documents and go out to bid.

Construction Contract

On February 22, 2017 an invitation to bid was released and three bids were received as shown below:

Krische Construction                                           $1,924,288.09

Colorado Designscapes                                          $2,274,000.00

Goodland Construction, Inc.                     $2,095,859.50**
** Note: this is a revised total bid amount based on corrections made to calculated bid quantities

 

Analysis completed by staff it has been determined that Goodland Construction, Inc. is the best overall contractor to complete the project based on the following factors:

 

                     Bid amount

                     Past work history/experience

                     Completion of similar projects

 

Construction Administration Contract

In order to successfully complete the construction of this project staff will contract with Design Concepts to serve as construction administrator on the Town’s behalf. As the consultant hired to complete the original master plan and construction documents, Design Concepts is most familiar with the overall project, Town expectations and standards, and can be trusted to serve in the best interest of the Town.

 

Project Budget Summary

The following is a summary of the total project costs and source of funding:

 

Costs:

Construction Contract                                                               $ 2,095,859.50

Contingency (10%)                                                               $    209,585.95

Construction Administration                                          $      32,880.00

                     Total                                                                                    $ 2,338,325.45

 

Funding:

Park Improvement Impact Fund                                           $ 1,671,570.95

Tree Impact Fund                                                               $      48,350.00

Developer Funds**                                                               $    618,404.50

                     Total                                                                                     $ 2,338,325.45

 

** Per the master development agreement for Flatiron Meadows, the developer is required to pay the costs associated with tap fees, final grading, soil preparation, purchase and installation of grass, purchase and installation of a permanent irrigation system (including electrical facilities for said system), landscaping within all adjacent right-of-ways and landscape buffers. In addition the developer is responsible to pay the Town water dedication fees in the amount of $549,498.40, over and above the $618,404.50 in the table above.

 

Once approved the anticipated project schedule is as follows:

                     Notice of Award                                                               April 26, 2017

                     Notice to Proceed                                          May 2, 2017

                     Construction Begins                                          May 15, 2017

                     Substantial Completion                                          Mid-November, 2017

 

ATTACHMENTS:                      

 

1.                     Star Meadows Park Master Plan Renderings

2.                     Goodland Construction, Inc. Corrected Bid