Title: Consideration of A Resolution Authorizing Award of a Construction Contract to Mountain Constructors, Inc., For the Vista Ridge Detention Pond Maintenance Project In The Amount of $39,155; And Setting Forth Details In Relation Thereto.
Attachments: 1. location map.pdf, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
SUBJECT: CONSENT
Title
Consideration of A Resolution Authorizing Award of a Construction Contract to Mountain Constructors, Inc., For the Vista Ridge Detention Pond Maintenance Project In The Amount of $39,155; And Setting Forth Details In Relation Thereto.

Body
DEPARTMENT: Public Works

PRESENTER/PREPARER: Gary Behlen, Public Works Director
Russell Pennington, Deputy Public Works Director
Wendi Palmer, Civil Engineer


FISCAL INFORMATION:
Cost as Recommended: $ 50,000
Balance Available: $ 73,650
Fund: Storm Drainage Operating
Budget Line Item Number: 520-70-110-605000-100149
New Appropriation Required: No


STAFF RECOMMENDATION:
Recommendation
Approving the Resolution to award said contract, authorizing the appropriate Town officer to execute said contract, authorizing Staff to expend contracted funds and contingency funds.

End
SUMMARY AND BACKGROUND OF SUBJECT MATTER:

It is important to ensure drainage facilities are maintained and in good repair for the protection of water quality and downstream properties. The 2016 budget includes funds for drainage facility maintenance and repair. Due to the age of the development and the number of storm water detention ponds, Vista Ridge was selected for review this year.

In order to ensure the storm water detention ponds are functioning properly, a Drainage Consultant was hired to assess the condition of the detention ponds. After reviewing the assessment, staff determined that the conditions warranted hiring a contractor to perform this maintenance. This assessment was used to bid a maintenance project in which 9 storm water detention ponds will be maintained.

An Invitation to bid was posted on the Town's website for the Vista Ridge Detention Pond Maintenance Project on October 4, 2016 to ensure that local contractors were notified about this project. No Erie contractors submitted bids.

The following bids were received on October 28, 2016:

Bid Information:
Contractor Bid Amount