Title: Consideration of A Resolution Approving an Amendment to a Design Build Contract With Fischer Construction, Inc., and JVA Consulting Engineers, Inc., For Setting the Guaranteed Maximum Price for the Water Plant Solids Handling Equipment Project In The Total Amount of $3,534,654, Authorizing an additional $3,346,589 be added to the Existing Design Build Contract; And Setting Forth Details In Relation Thereto.
Attachments: 1. Resolution
SUBJECT: CONSENT AGENDA
Title
Consideration of A Resolution Approving an Amendment to a Design Build Contract With Fischer Construction, Inc., and JVA Consulting Engineers, Inc., For Setting the Guaranteed Maximum Price for the Water Plant Solids Handling Equipment Project In The Total Amount of $3,534,654, Authorizing an additional $3,346,589 be added to the Existing Design Build Contract; And Setting Forth Details In Relation Thereto.

Body
DEPARTMENT: Public Works

PRESENTER/PREPARER: Gary Behlen, Public Works Director
Russell Pennington, Deputy Public Works Director
Wendi Palmer, Civil Engineer
Bruce Chameroy, Chief Water Plant Operator

FISCAL INFORMATION:
Additional Cost as Recommended: $ 3,485,700
Balance Available: $ 3,485,700 with the approval of the second supplemental budget
Fund: Water
Budget Line Item Number: 500.70.110.605000.100185
New Appropriation Required: No

STAFF RECOMMENDATION:
Recommendation
Approve the Resolution to amendment said contract, authorize the appropriate Town officer to execute said amendment, authorize Staff to expend contracted funds and contingency funds.

End
SUMMARY AND BACKGROUND OF SUBJECT MATTER:

The 2016 budget includes funds to design and construct improvements for solids/sludge handling equipment and to repurpose the old water treatment plant at the Water Treatment Facility. The existing building will house the solids handling equipment, the powder activated carbon system, and sodium permanganate system for taste and odor control and additional treatment. The solids handling equipment is necessary to be able to process our increasing water treatment waste as the Town continues to grow.

At the May 10, 2016 Board Meeting, the design phase of a design build project was awarded to Fischer Construction, Inc., and JVA Consulting Engineers, Inc. During the design phase a Guaranteed Maximum Price (GMP) would be determined after the technology was selected and the design is complete. At that ti...