File #: 16-349    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 9/27/2016 In control: Town Council
On agenda: 9/27/2016 Final action: 9/27/2016
Title: A Resolution Approving a Change Order Request for Town Hall Sand-Stone Selection at Main Entrance and Electrical Code Issue.in the amount of $105,000.00.
Attachments: 1. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: CONSENT

A Resolution Approving a Change Order Request for Town Hall Sand-Stone Selection at Main Entrance and Electrical Code Issue in the amount of $105,000.00.

Title

 

Body

DEPARTMENT:                                                               Public Works

 

PRESENTER:                                                               Russell Pennington, Public Works Deputy Director

                                          Raelynn Ferrera, Public Works Project Coordinator

FISCAL INFORMATION:

Cost as Recommended:                                                               $105,000.00

Balance Available:                                                               $184,751.42

Fund:                                                                                                         Public Facilities Impact

Budget Line Item Number:                                           310.70.110.605000.100151

New Appropriation Required:                                          Yes

 

STAFF RECOMMENDATION: Approve Resolution authorizing execution of said Change Order, appropriating additional funds and authorizing Staff to expend funds.

Recommendation

 

End

SUMMARY AND BACKGROUND OF SUBJECT MATTER: On August 9, 2016, The Board of Trustees consensus was to approve the "Red Sandstone Option" for the Town Hall Entrance. The additional cost for the sandstone option to be used in place of the brick option is $75,000.00.

 

During the installation of the electrical breakers for the lighting in Phase I of the Town Hall Remodel, it was discovered that the electrical system throughout the building was not up to the current building code.

 

The current contract assumed that the electrical system met the current building code, however in this case once the electrician began the work, three significant issues were discovered:

 

1.                     Several circuits had been changed to emergency circuits during previous construction.

                     The building code does not allow electrical panels to be used as race ways for emergency circuits.

2.                     The proper number of neutral circuits are not installed.

                     The building code requires a minimum number of neutral circuits installed for every active circuit to allow for surge protection.

3.                      Several existing raceways have exceeded capacity.

                     The existing wiring in the raceways creates an electrical current, and the current amount running through the raceways is creating more friction than allowed per the building code.

Our Contractor, Fransen Pittman has worked with the electrical sub-contractor to obtain a time and material not to exceed proposal to resolve the issue for the entire building, bringing all of Town Hall into compliance.

 

The not to exceed amount for the additional electrical work is $30,000. This additional amount will be added to the existing contract and will be performed under the original contract terms as a change order. All remaining funds will be returned to the Town.

 