Town of Erie
File #: 16-266    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 7/12/2016 In control: Town Council
On agenda: 7/26/2016 Final action:
Title: Consideration Of A Resolution Authorizing Award Of A Construction Contract To WL Contractors, Inc. For The Arapahoe Road And 119th Street Signal Improvements Project In The Amount Of $30,283.00; And Setting Forth Details In Relation Thereto.
Attachments: 1. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT:

Title

Consideration Of A Resolution Authorizing Award Of A Construction Contract To WL Contractors, Inc. For The Arapahoe Road And 119th Street Signal Improvements Project In The Amount Of $30,283.00; And Setting Forth Details In Relation Thereto.

 

Body

DEPARTMENT: Public Works

 

PRESENTER:                      Gary Behlen, Public Works Director

                                                               Jody Lambert, Operations and Maintenance Manager

 

FISCAL INFORMATION:

Cost as Recommended:                                          $ 36,400

Balance Available:                                                               $ 50,000

Fund:                                                                                                         General

Budget Line Item Number:                                           100-70-710-605000-100205

New Appropriation Required:                                          No

 

STAFF RECOMMENDATION: Approving the Resolution to award said contract, authorizing the appropriate Town officer to execute said contract, authorizing Staff to expend contracted funds and contingency funds.

Recommendation

 

End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

The amended 2016 budget includes funds to upgrade the video detection system on the traffic signal at the Arapahoe Road and 119th Street intersection.  Upgrades include the camera detection, processor, heads, and wiring. These upgrades will allow the intersection to have full video detection which provides more efficient signal operation.

 

Staff requested a quote for this work from W.L. Contractors Inc. The Town uses WL for the annual maintenance agreement and on-call services for all signal repairs.  Staff received a quote for $30,283.00 to complete the upgrades. Staff recommends awarding the construction contract for the Arapahoe Road and 119th Street Signal Improvements Project to WL Contractors, in the amount of $30,283.00.

 

Summary

                     Construction Contract                                                               $    30,283

                     Contingency                      (20%)                                                               $      6,117

                     Total                                                                                                         $    36,400

 

Project Schedule

                     Notice of Award                                                               July, 2016                                          

                     Notice to Proceed                                                                August, 2016

                     Construction Complete                                           Fall, 2016

 

ATTACHMENTS:                      

a.                     Resolution