Title: Consideration of A Resolution Authorizing Award of a Construction Contract To Spiegel Industrial, LLC, For the 1.5 MG Zone 3 Water Storage Tank Improvements Project In The Amount of $460,000; And Setting Forth Details In Relation Thereto.
Sponsors: Public Works
Attachments: 1. 1 5mgTankVM.pdf, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
SUBJECT: CONSENT AGENDA
Title
Consideration of A Resolution Authorizing Award of a Construction Contract To Spiegel Industrial, LLC, For the 1.5 MG Zone 3 Water Storage Tank Improvements Project In The Amount of $460,000; And Setting Forth Details In Relation Thereto.
Body
DEPARTMENT: Public Works

PRESENTER/PREPARER: Gary Behlen, Public Works Director
Russell Pennington, Deputy Public Works Director
Wendi Palmer, Civil Engineer


FISCAL INFORMATION:
Cost as Recommended: $522,000
Balance Available: $604,678 (Pending 2015 funds to be rolled-over)
Fund: Water
Budget Line Item Number: 500-70-110-605000-100137
New Appropriation Required: No

STAFF RECOMMENDATION:
Recommendation
Approving the Resolution to award said contract, authorizing the appropriate Town officer to execute said contract, authorizing Staff to expend contracted funds and contingency funds.

End
SUMMARY AND BACKGROUND OF SUBJECT MATTER:
The 2016 budget includes funds to design and construct improvements to the 1.5 MG Zone 3 Water Storage Tank.
During an inspection of the 1.5 mg water tank in 2014, it was discovered that there were leaks at the pipe penetrations of the tank. A remedial repair was done in 2014 using divers to complete the repair. At that time it was not practical to drain the tank for a permanent repair.
The Town completed the construction of the 4 MG Zone 3 Water Storage Tank early spring of 2015. With the new 4 MG tank operational, Town Staff has been able to take the 1.5 MG tank out of service and further assess the repairs needed to correct the leaks. In addition to repairing the leaks, other improvements to the tank have been designed and include adding a mixing system and lining the concrete tank. Both the mixing system and tank liner will help with water quality in the tank and help the tank operate in the same manner as the new 4 MG tank next to it.
Burns & McDonnell assisted the Town in preparing the design and bid documents for the improvement...