SUBJECT:
Title
A Resolution of the Town Council of the Town of Erie Approving an Agreement for Professional Services with Kimley-Horn and Associates, Inc. for the Sheridan Parkway and Ridgeview Drive Traffic Signal
Body
DEPARTMENT: Public Works
Department
PRESENTER(S): Todd Fessenden, Public Works Director
Jonathan Williams, Civil Engineer II
First Name, Last Name, Title
FISCAL SUMMARY:
Cost as Recommended: $132,441
Balance Available: $0
Budget Line Item Number: 300-70-110-605000-100412
New Appropriation Required: Yes
POLICY ISSUES:
None
STAFF RECOMMENDATION:
Recommendation
Approve the Resolution
End
SUMMARY AND BACKGROUND OF SUBJECT MATTER:
The Town of Erie requested our consultant, Fox Tuttle Associates, to perform a Signal Warrant Analysis at the intersection of Sheridan Parkway and Ridgeview Drive. The results of the signal warrant study dated March 31, 2023, determined that a signal is warranted at this time.
Following this determination, the Town of Erie met and coordinated with the City and County of Broomfield regarding funding and maintenance of the signal because a portion of the intersection is located within Broomfield’s jurisdiction. Broomfield agreed to share in the funding through an IGA under separate process. Once the separate IGA is complete reimbursement for this signal project will occur. The purpose of this funding request is to begin the design effort for the signal to expedite construction of the signal in 2024. Staff anticipates that the design effort can be completed in approximately 6 months thus allowing bid and construction to occur through the summer months. Upon completion the Town of Erie will own and maintain the signal.
BOARD PRIORITY(S) ADDRESSED:
ü Well-Maintained Transportation Infrastructure
ü Safe and Healthy Community
ATTACHMENT(s):
1. Resolution
2. Agreement