Title: A Resolution of the Town Council of the Town of Erie Approving a Grant Agreement with the Division of Aeronautics for Erie Municipal Airport Pavement Maintenance
Attachments: 1. Resolution 26-061, 2. Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: 

Title
A Resolution of the Town Council of the Town of Erie Approving a Grant Agreement with the Division of Aeronautics for Erie Municipal Airport Pavement Maintenance

 

Department

DEPARTMENT:                     Public Works

Presenter

PRESENTER(S):                     David Pasic, Public Works Director

end

 

Time

TIME ESTIMATE: 0 minutes
end

 

Fiscal
FISCAL SUMMARY:

Cost as Recommended:                                           $300,000

Balance Available:                                                                 $0

Budget Line Item Number:                       530-00-000-411200-100168

New Appropriation Required:                       Yes


Policy

POLICY ISSUES:

Maintaining Town Infrastructure, such as the Airport pavement meets the Town’s policy of ensuring safety and meeting our Federal Aviation Authority (FAA) Grant Assurances. Doing so the federal and state grants are fiscally responsible.

 

Recommendation

STAFF RECOMMENDATION:

Approve the Resolution to receive the grant funding.

Body

SUMMARY/KEY POINTS

                     Accepting Colorado Division of Aeronautics (CDOA) grant funding for the airport

                     Pavement maintenance needs at the airport

                     This grant is funded 90% by CDOA and 10% Town match.

 

BACKGROUND OF SUBJECT MATTER:

The pavement maintenance project at the Erie Municipal Airport (EIK) will include joint seal replacement, crack sealing, spall repair, and new airfield markings for select locations on Runway 16/34, Taxiway A and connectors, and the main apron. The project will include pre-design, design, bidding, construction, inspection, and project closeout. The pavement maintenance project will fix areas of crumbling or failing concrete, replace failed joint sealant, seal existing racks and provide new airfield pavement markings. The project will increase the useful life of Runway 16/34, Taxiway A and main apron.


priorities

.

attachments

ATTACHMENT(S):

1.                     Resolution

2.                     Agreement