Skip to main content
Town of Erie
File #: 16-171    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 4/28/2016 In control: Town Council
On agenda: 5/10/2016 Final action:
Title: A Resolution Requesting Additional Funds for Unforeseen Repair Items at the Erie Community Center And Setting Forth Details in Relation Thereto
Attachments: 1. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
SUBJECT: CONSENT
A Resolution requesting additional funds for unforeseen repair items at the Erie Community Center And Setting Forth Details in Relation Thereto
Title
Body
DEPARTMENT: Public Works

PRESENTER: Gary Behlen, Public Works Director
Ed Mestas, Facilities Maintenance Division Manager

FISCAL INFORMATION:
Cost as Recommended: $20,790.00
Balance Available: $0.00
Fund General
Budget Line Item Number: 100.70.440.522100.000000
New Appropriation Required: Yes

STAFF RECOMMENDATION: Approve Resolution authorizing execution of said work, and authorizing Staff to expend funds for purchase.
Recommendation
End
SUMMARY AND BACKGROUND OF SUBJECT MATTER: The 2016 operating budget does not have funds for emergency or unforeseen items. Therefore it is necessary for us to request these additional funds for the following maintenance items at the Erie Community Center.

Repair Components of two Roof Top Units (RTU)
$8,450.00
Replace Pump and Ball Valves on the Domestic Hot Water
$5,560.00
Remove and Replace Concrete Steps
$4,890.00
Total
$18,900.00
10% Contingency
$1,890.00
Total
$20,790.00



During Staff's routine preventative maintenance inspections, facilities staff came across multiple issues at the Erie Community Center.

The Heating Ventilation and Air Conditionings (HVAC) equipment has been in service for the last 8 years, running 7 days a week 24 hours a day, therefore it is quickly approaching it life expectancy. Staff inspected all of the Roof Top Units (RTU) which operate the HVAC. Staff is recommending that certain components on two of the RTUs be repaired and/or replaced in order to extend the life of the two RTUs.

After inspecting the Domestic hot water service for the center, Staff has identified that the system is in need of a new pump and ball valves. In order for this work to be performed, the water service to the building will need to be shut off after regular business hours.

By being proactive...