Town of Erie
File #: 20-374    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 6/25/2020 In control: Town Council
On agenda: 7/14/2020 Final action:
Title: A Resolution of the Board of Trustees of the Town of Erie Approving the First Amendment to the Birdhouse Development Agreement
Attachments: 1. Resolution, 2. First Amendment to Development Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
SUBJECT: CONSENT
Title

A Resolution of the Board of Trustees of the Town of Erie Approving the First Amendment to the Birdhouse Development Agreement

Body
DEPARTMENT: Planning and Development

PRESENTER: Fred Starr, Planning and Development Director

FISCAL INFORMATION: Not applicable
Cost as Recommended:
Balance Available:
Budget Line Item Number(s):
New Appropriation Required:

STAFF RECOMMENDATION:
Recommendation

Approve the resolution authorizing the First Amendment to the Birdhouse Development Agreement.

End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

On December 10, 2019 the Board of Trustees approved the Development Agreement with RTR Birdhouse Holdings, LLC as a part of the approval for the Final Plat of the Town of Erie Skiba Amendment Subdivision.
Section 2 (b) of the original development agreement specified that the public Stormwater improvements, identified in Exhibit "B" of the development agreement, were to be installed by June 30, 2020. The ability of this work to be completed by RTR Birdhouse Holdings, LLC has been affected by the recent disruption to construction services which would have been used to complete this work. Work to be completed also would require closing the alley which would create a public safety risk during the current closure of the 500 Block. This will provide an extension to allow Birdhouse to complete the storm water improvements in the fall.
Section 6(a) of the original development agreement required the applicant to provide an Improvement Guarantee in the amount of $39,520.37 for the work identified in Exhibit "B". Since the time of the original cost estimate, the applicant identified additional costs for the work, which have been reviewed and verified the Town. The total cost for this work is now estimated to be $92,500.00 which includes the 115% ...