SUBJECT:
Title
A Resolution of the Town Council of the Town of Erie Approving the Third Amendment to Contract Manager at Risk Contract with Fransen Pittman Construction for the Police Department Expansion and Remodel Project
Department
DEPARTMENT: Public Works
Presenter
PRESENTER(S): David Pasic - Public Works Director
Chad Alexander - Facilities Manager
end
Time
TIME ESTIMATE: 0 minutes
end
Fiscal
FISCAL SUMMARY:
Cost as Recommended: $29,318,751
Balance Available: $35,051,487
Fund Police Facility Impact Fund
Line Item Number: 325-70-110-605000-100391
New Appropriation Required: No. These funds will be reimbursed by Certificates of Participation financing
Policy
POLICY ISSUES:
The policy implications of this item include whether to expend funds on the expansion and remodel project for Erie Police Department facility to secure subcontractor agreements and to procure the final bid package materials and equipment. Approving this item is a step toward the execution of Certificates of Participation.
Recommendation
STAFF RECOMMENDATION:
Approve the Resolution
Body
SUMMARY/KEY POINTS
* This resolution ensures the Police Department Expansion and Remodel project stays on schedule and current budget projections are maintained.
* Council approval is needed to secure the most competitive and predictable pricing available to procure items and ensure items are received when needed for the project.
* The combined total of the First, Second, and Third Amendment costs together with the Phase 1 Pre-Construction Services fee establishes the Guaranteed Maximum Price (GMP), as defined in the CMaR Contract between Fransen Pittman and the Town of Erie. This final GMP represents the total fixed limit of construction cost for the Project.
BACKGROUND OF SUBJECT MATTER:
On Sept. 10, 2024, the Town Council Approved the Award of a Consultant Contract to D2C Architects for the Police Department Expansion and Remodel Project Desig...
Click here for full text