Skip to main content
Town of Erie
File #: 25-247    Version: 1 Name:
Type: General Business Status: Agenda Ready
File created: 4/8/2025 In control: Town Council
On agenda: 5/13/2025 Final action:
Title: A Resolution of the Town Council of the Town of Erie Approving an Agreement with RockSol Consulting Group Inc. for Construction Management Services
Attachments: 1. Resolution 25-069, 2. Agreement, 3. Vicinity Map, 4. Executed on call construction management contract
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
SUBJECT:
Title
A Resolution of the Town Council of the Town of Erie Approving an Agreement with RockSol Consulting Group Inc. for Construction Management Services
Body

DEPARTMENT: Public Works
Department

PRESENTER(S): David Pasic, Director of Public Works
Jonathan Williams, Civil Engineer
First Name Last Name, Title

FISCAL SUMMARY:
Cost as Recommended: $138,540.36, $138,540.36
Balance Available: $2,600,000, $4,577,596
Budget Line Item Number: 300-70-110-605000-100389
300-70-110-605000-100093
New Appropriation Required: No

Funding for this project is anticipated to be split 50%/50% between the South Roundabout Project and County Line Road- Erie Parkway to Mitchell Way projects due to the method of funding established as part of the construction contract identified as Schedule A and Schedule B.

POLICY ISSUES:
Weather to support the use of budgeted funds to hire a construction management firm to provide construction oversight for this project.

STAFF RECOMMENDATION:
Recommendation
Approve the Resolution authorizing Construction Management Services General Services Agreement with RockSol Consulting Group Inc.
End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:
Earlier this year Town staff solicited proposals for Construction Management (CM) Services to assist in providing adequate oversight of various on-going construction projects within the Town. Four firms were selected for the Towns shortlist to provide the on-call services. RockSol Consulting was identified as one of the four firms selected.

Staff contacted RockSol to request a cost for construction oversight services for the South Roundabout and the County Line Road - Mitchell Way to Erie Parkway projects based on the hourly rates identified in the CM Services agreement. Staff coordinated with Rocksol on the anticipated effort necessary for services. Work will include daily oversight and inspection services. Quality Assurance geotechnical testing, weekly project co...

Click here for full text