Title: A Resolution of the Town Council of the Town of Erie Approving a Second Amendment to Agreement for Professional Services with Ulteig Operations, LLC for Construction Management Services for the Weld County Road 3 Bridge Replacement Improvements
Attachments: 1. Resolution 25-187, 2. Second Amendment, 3. Vicinity Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: 

Title
A Resolution of the Town Council of the Town of Erie Approving a Second Amendment to Agreement for Professional Services with Ulteig Operations, LLC for Construction Management Services for the Weld County Road 3 Bridge Replacement Improvements

 

Department

DEPARTMENT:                     Public Works
    

    
Presenter

PRESENTER(S):                     David Pasic, Public Works Director

Kieth Fiebig, Town Engineer
end

 

Time

TIME ESTIMATE: 0 minutes
end

For time estimate: please put 0 for Consent items.

 

Fiscal
FISCAL SUMMARY:

Cost as Recommended:                                           $ 22,000

Balance Available:                                                                 $ 111,029

Fund                                                                                                          Capital Improvements Fund

Line Item Number:                                                                110-70-425-605000-100085

New Appropriation Required:                       No


Policy

POLICY ISSUES:

The policy item here is whether to expend budgeted funds for the purpose of providing project management services for the grant funded bridge replacement.

 

Recommendation

STAFF RECOMMENDATION:

Approve the Resolution to amend the Agreement.

Body

SUMMARY/KEY POINTS

                     This Second Amendment to Professional Services Agreement (PSA) will facilitate completion of consultant project management, inspection and documentation services needed to complete construction on schedule.

                     The project is progressing toward Final Completion anticipated in late November 2025.

 

BACKGROUND OF SUBJECT MATTER:

The following prior items were authorized:

 

                     On Nov. 12, 2024, the Town Council approved a PSA with Ulteig Operations to provide Construction Management Services to support construction for this project.

 

                     On July 7, 2025, staff authorized the First Amendment to PSA to extend services through April 2025 to accommodate a schedule extension and inspect corrective construction work for impact attenuators, concrete transitions, bridge rails, and rip-rap installation; and review added traffic control and asphalt submittals.

 

The current resolution before the Council includes the Second Amendment to the PSA with Ulteig Operations for extended project management, construction inspection, and documentation services, above the effort originally anticipated.  The additional services were related to corrective construction of the concrete bridge abutments and asphalt roadway pavement; and a Town directed schedule extension to November 2025.  Approval of this Amendment will keep the project progressing on schedule to Final Completion.

Staff recommend approving the Second Amendment with Ulteig Operations to cover the additional services scope. There are adequate funds in the 2025 CIP project budget.

 

Original Contract Amount:                                          $ 178,500

1st Amendment:                                                                $   22,312

2nd Amendment:                                                                $ 22,000

Total New Contract Amount                     $ 222,812

 

 