Title: Consideration of A Resolution Authorizing Award of a Construction Contract to Mountain Constructors, Inc., For the Vista Ridge Detention Pond Maintenance Project In The Amount of $39,155; And Setting Forth Details In Relation Thereto.
Attachments: 1. location map.pdf, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT:                     CONSENT

Title

Consideration of A Resolution Authorizing Award of a Construction Contract to Mountain Constructors, Inc., For the Vista Ridge Detention Pond Maintenance Project In The Amount of $39,155; And Setting Forth Details In Relation Thereto.

 

Body

DEPARTMENT:                                                               Public Works

 

PRESENTER/PREPARER:                     Gary Behlen, Public Works Director

                                                                                                         Russell Pennington, Deputy Public Works Director

                                          Wendi Palmer, Civil Engineer

 

 

FISCAL INFORMATION:

Cost as Recommended:                                          $ 50,000

Balance Available:                                                               $ 73,650

Fund:                                                                                                         Storm Drainage Operating

Budget Line Item Number:                                           520-70-110-605000-100149

New Appropriation Required:                                          No

 

 

STAFF RECOMMENDATION:

Recommendation

Approving the Resolution to award said contract, authorizing the appropriate Town officer to execute said contract, authorizing Staff to expend contracted funds and contingency funds.

 

End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

 

It is important to ensure drainage facilities are maintained and in good repair for the protection of water quality and downstream properties. The 2016 budget includes funds for drainage facility maintenance and repair.  Due to the age of the development and the number of storm water detention ponds, Vista Ridge was selected for review this year.  

 

In order to ensure the storm water detention ponds are functioning properly, a Drainage Consultant was hired to assess the condition of the detention ponds.  After reviewing the assessment, staff determined that the conditions warranted hiring a contractor to perform this maintenance. This assessment was used to bid a maintenance project in which 9 storm water detention ponds will be maintained.

 

An Invitation to bid was posted on the Town’s website for the Vista Ridge Detention Pond Maintenance Project on October 4, 2016 to ensure that local contractors were notified about this project. No Erie contractors submitted bids.

 

The following bids were received on October 28, 2016:

 

Bid Information:

Contractor                                                                                                                              Bid Amount

Mountain Constructors Inc.                                                                                    $   39,155.00

Frontier Environmental Services, Inc.                                          $   39,950.00

Dan's Custom Construction                                                                                    $   44,500.00

Rocky Mountain Equipment.                                                                                    $   45,550.00

LMX Services Cam Corp                                                                                    $   85,350.00

MSI Enterprises                                                                                                         $   86,600.00

ESCO Construction Company                                                               $ 209,035.00

 

The low bidder is Mountain Constructors Inc. Mountain Constructors has worked for the Town of Erie in the past. They constructed the initial phase of Erie Parkway east of County Line Road, constructed the A3 Mid Field and East Taxiway Connectors at the Erie Municipal Airport, the Coal Creek Trail Extension from Cheesman Street to Reliance Park, flood repairs to the irrigation pond east of Erie Commons and the WCR 5 Bridge Repair. Staff has reviewed Mountain Constructors, Inc.’s bid and found it to be acceptable. 

 

Staff is recommending awarding the construction contract for the Vista Ridge Detention Pond Maintenance Project to Mountain Constructors Inc., in the amount of $39,155.

 

Summary

                     Construction Contract                                                               $    39,155

                     Contingency                                                                                     $    10,845

                     Total                                                                                                         $    50,000

 

Project Schedule

                     Notice of Award                                                               November 16, 2016                                          

                     Notice to Proceed                                                                November 30, 2016

                     Construction Complete                                           Spring, 2017

 

ATTACHMENTS:

a.                     Location Map

b.                     Resolution