Legislation Details

File #: 24-418    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 8/21/2024 In control: Town Council
On agenda: 9/24/2024 Final action:
Title: A Resolution of the Town Council of the Town of Erie Approving a Construction Contract with Hudick Excavating, Inc. for the Zone 3 Weld County Road 7 Waterline Improvements
Attachments: 1. Resolution 24-139, 2. Construction Contract, 3. Vicinity Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: 

Title

A Resolution of the Town Council of the Town of Erie Approving a Construction Contract with Hudick Excavating, Inc. for the Zone 3 Weld County Road 7 Waterline Improvements

Body

 

DEPARTMENT:                     Public Works

Department

 

PRESENTER(S):                     David Pasic, Interim Public Works Director

                                                               Zachary Ahinga, Civil Engineer

First Name Last Name, Title

 

FISCAL SUMMARY:

Cost as Recommended:                                           $ 5,492,325.00

Balance Available:                                                                 $ 11,476,896.59

Fund:                                                                                                         Water

Budget Line Item Number:                       500-75-110-605000-100421

New Appropriation Required:                       No

 

POLICY ISSUES:

None.

 

STAFF RECOMMENDATION:

Recommendation

Approve the Resolution authorizing the construction contract with Hudick Excavating, Inc.

End

 

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

The Zone 3 Weld County Road (WCR) 7 Waterline Improvements project is needed to supply water to the Summerfield development by late 2025 to satisfy the Town’s obligation under the 2013 Summerfield Annexation Agreement. The Summerfield development is located south of Highway 52 and west of WRC 7.

 

On July 12, 2022, Council approved a Professional Services Agreement with Burns and McDonnell Engineering Company to complete the construction documents for this project.  The project has been designed with sufficient capacity to meet:

 

1.                     In the interim, adequate water supply for the Summerfield development by late

2025 and;

2.                     The future water supply demands for the Town’s Erie Gateway properties to the east of WCR 7 as well as other properties if annexed.

 

This construction contract requires the contractor to implement a full-road way closure (with traffic detours) of WCR 7 from WCR 12 northward to Highway 52 allowing only local traffic to pass through the work zone. Further, the contract requires completion of this pipeline segment by March 31, 2025, and requires completion of the remainder of the project in late October 2025.

 

Staff posted a request for bids on Bidnet Direct for the Zones 3 Weld County Road 7 Waterline Improvements on July 23, 2024.

 

Staff held a non-mandatory pre-bid meeting on July 31, 2024.

 

The Town received the following bids on Aug. 23, 2024:

 

Bid Information:

Contractor Name

Bid Amount

Bid Bond included

Hudick Excavating, Inc.

$ 5,109,140.00

Yes

RCD Construction, Inc.

$ 5,257,473.37

Yes

Global CM, LLC

$ 5,353,374.87

Yes

Colorado Civil Infrastructure, Inc.

$ 5,800,000.00

Yes

Elevated Excavating, Inc.

$ 5,807,615.95

Yes

Timber Wolf Excavating, Inc.

$ 5,874,605.00

Yes

Reynolds Construction, LLC

$ 6,230,127.00

Yes

SMH West

$ 6,890,093.00

Yes

TRC Construction, Inc.

$ 6,899,452.00

Yes

Global Underground Corporation

$ 6,930,273.00

Yes

GoodLand Construction, Inc.

$ 6,963,534.00

Yes

American West Construction, LLC

$ 7,351,320.00

Yes

Fiore and Sons

$ 7,540,070.09

Yes

Iron Woman Construction

$ 8,803,877.00

Yes

 

 

 

Engineer’s Estimate

$ 13,418,481.80

 

 

The low bidder is Hudick Excavating, Inc. Staff checked their references, and determined they are qualified to construct this project. Accordingly, staff recommends awarding the construction contract for the Zones 3 Weld County Road 7 Waterline Improvements project to Hudick Excavating, Inc., for the bid amount of $5,109,140.00 and a contingency amount of $383,185.00 for a total contract amount of $5,492,325.  In addition to this resolution, on the agenda tonight is a resolution approving a Third Amendment to Professional Services Agreement for Construction Management Services for the Zones 3 Weld County Road 7 Waterline Improvement (Consent Agenda 24-419).

 

Fiscal Impact:

The 2024 Water Fund Budget has $11,476,896.59 appropriated for construction of Zones 3 Weld County Road 7 Waterline Improvements.

 

Cost Summary:

Item

Estimated Cost

Construction Management Services CM Services

$   199,066.00

CM Services Contingency (10.0%)

$     20,090.00

Construction Bid Amount

$ 5,109,140.00

Construction Contingency (7.5%)

$   383,185.00

Total Estimated Construction Cost

$5,711,481.00

 

 

COUNCIL PRIORITY(S) ADDRESSED:

ü                     Prosperous Economy

ü                     Safe & Healthy Community

ü                     Effective Governance

ü                     Fiscally Responsible

 

ATTACHMENT(S):                      

1.                     Resolution 24-139

2.                     Construction Contract

3.  Vicinity Map