Title: A Resolution Authorizing Award of a Construction Contract To Preferred Garages, Inc., For the Leon A. Wurl (L.A.W.) Service Center Storage Building In The Amount of $48,997 for Construction and $5,003 for Contingency.
Attachments: 1. Construction Agreement, 2. Facility Vicinity Map, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: CONSENT AGENDA

Title

A Resolution Authorizing Award of a Construction Contract To Preferred Garages, Inc., For the Leon A. Wurl (L.A.W.) Service Center Storage Building In The Amount of $48,997 for Construction and $5,003 for Contingency.

 

Body

DEPARTMENT:                                                               Public Works

 

PRESENTER/PREPARER:                     Todd Fessenden, Public Works Director

Eric Banker, Facility Operation Services Supervisor

                                                                                                         Wendi Palmer, Civil Engineer

 

FISCAL INFORMATION:

Cost as Recommended:                                          $ 54,000

Balance Available:                                                               $ 140,500.00

Fund:                                                                                                         Public Facilities Impact

Budget Line Item Number:                                           310-70-110-605000-100218

New Appropriation Required:                     No

 

STAFF RECOMMENDATION:

Recommendation

Approve the resolution to award said contract, authorize the appropriate town officer to execute said contract, authorize staff to expend contracted funds and contingency funds.

End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

 

The 2017 Public Facilities Impact Fund Budget has funds appropriated for the design and construction of a Facilities Storage Building at the L.A.W. Service Center site.

 

The addition of a new storage building required a site plan amendment. OZ Architecture, who designed the L.A.W. Service Center was hired to design the Facilities Storage Building and prepare the documents needed for a Site Plan Amendment. Notice that the review and approval of the site plan amendment was complete was given on March 14, 20018 and the amendment was signed on March 20, 2018.   

 

An Invitation to bid was posted on the Town’s website for the L.A.W. Service Center Storage Building on March 15, 2018 to ensure that local contractors were notified about this project. No Erie contractors submitted bids.

 

The following bids were received on April 26, 2018:

 

Bid Information:

Contractor                                                                                                                              Bid Amount                                          

TCC Corporation                                                               $166,784

Barba & Sons                                                                               $171,925

PG Arnold Construction                                                                               $211,818                                          

 

Due to the bid coming in over budget, staff meet with TCC Corporation to Value Engineer the building in hopes of it coming in within budget. They were only able to reduce the bid by approximately $20,000.

 

With the project still coming in over budget, staff reached out to separate contractors for constructing the building, providing electrical service and fencing relocation. In addition, staff will do the trenching for electrical and paint the building to reduce the scope of what will be contracted for construction. With this extra effort to get the project within budget, the following summarizes the various contractors providing contracts:

 

Building Construction:

Contractor                                                                                                                              Amount                                          

Preferred Garages, Inc.                                                          $48,997

Rocky Mountain Storage Barns, Inc.                                                $59,920

 

Electrical Work:

Contractor                                                                                                                              Amount                                          

Couper Electric, LLC                                                               $15,770

South Paw electric Corp.                                                     $16,624

North/Western Electrical Corp.                                                        $28,649                     

 

Fence Work:

Contractor                                                                                                                              Amount                                          

Custom Fence and Supply, Inc.                                                               $  2,571

 

The total cost to construct the L. A. W. Service Center Storage Building is:                     

Preferred Garages, Inc.                                                          $48,997

Couper Electric, LLC                                                               $15,770

Custom Fence and Supply, Inc.                                                               $  2,571

Sub Total                                                                                               $67,345

10% Contingency                                                                          $  6,655

Total                                                                                                                                       $74,000

 

Staff is recommending awarding the construction contract for the L.A.W. Service Center Storage Building to Preferred Garages, Inc., in the amount of $ 48,997. The electrical and fence contracts will be handled by Staff as they are below $25,000.

 

Building Construction

                     Construction Contract                                                               $    48,997

                     Contingency                      (10%)                                                                                    $      5,003

                     Total                                                                                                                              $    54,000

 

Project Schedule

                     Notice of Award                                                               July 11, 2018                                          

                     Notice to Proceed                                                                July 25, 2018

                     Construction Complete                                                    Fall 2018

 

ATTACHMENTS:                      

a.                     Vicinity Map

b.                     Construction Agreement

c.                     Resolution