Skip to main content
Town of Erie
File #: 25-555    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 10/1/2025 In control: Town Council
On agenda: 10/28/2025 Final action:
Title: A Resolution of the Town Council of the Town of Erie Approving a Funding Agreement with Xcel Energy for Design and Relocation of a Gas Line at County Line Road and Austin Avenue
Attachments: 1. Resolution 25-168, 2. Final Agreement, 3. Exhibit Plan Profile - Gas Line
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: 

Title
A Resolution of the Town Council of the Town of Erie Approving a Funding Agreement with Xcel Energy for Design and Relocation of a Gas Line at County Line Road and Austin Avenue

Department

DEPARTMENT:                     Public Works

    


Presenter

PRESENTER(S):                     David Pasic, Public Works Director

Kieth Fiebig, Town Engineer
end

 

Time

TIME ESTIMATE: 0 minutes
end

 

Fiscal
FISCAL SUMMARY:

Cost as Recommended:                                           $742,409.11

Balance Available:                                                                 $914,018.00

Fund                                                                                                          Transportation Impact Fund

Line Item Number:                                                                 300-70-110-605000-100093

New Appropriation Required:                       No


Policy

POLICY ISSUES:

The policy issue before Council is whether to expend budgeted funds for the design and relocation of a previously unidentified Xcel high-pressure gas line on the western side of County Line Road at Austin Avenue.

 

Recommendation

STAFF RECOMMENDATION:

Approve the Resolution.

Body

SUMMARY/KEY POINTS

                     A previously unidentified Xcel gas line needs to be lowered at the intersection of County Line Road and Austin Avenue before the roundabout construction can be fully completed. 

                     The gas line must be lowered by a pre-approved Xcel subcontractor.

                     Utility easements in this location supersede the Town’s easements. Consequently, the Town is financially responsible for the project.

                     Staff is coordinating with Xcel to keep as many lanes of traffic open as possible while this relocation takes place. 

 

BACKGROUND OF SUBJECT MATTER:

Six gas lines are located within the County Line Road corridor. Five of the lines are high pressure transmission lines. Each utility company secured easements in the early 1980’s to allow construction of the transmission lines across private property generally to the west of the County Line Road Right of Way (ROW). These easements pre-date the Town ROW that exists today, specifically Austin Avenue. Because these are transmission lines and the utilities’ easements pre-date the Town’s ROW, the cost of relocating the lines is not covered by the Town’s franchise agreement with Xcel, and the cost to relocate is the Town’s responsibility.  

 

During the design phase of the County Line Road and Austin Avenue Roundabout, contractor’s potholed each utility line in two locations to determine the depth of the lines. This is consistent with the standard approach to locating utilities during design. Based on that pothole information, the elevation of the lines was determined to be acceptable when compared to existing and final grades of the newly constructed roadway. However, once construction began, the contractor performed additional potholing for utility lines in more locations through the corridor, which is consistent with the standard approach when construction begins.  This 2nd potholing showed that one gas line owned by Xcel rose in elevation for a short segment through the intersection of Austin Avenue before dropping again. The elevation of the existing gas line is only 12 inches below the top of asphalt of the final roadway section. This elevation is too shallow to allow roadway traffic to cross the line and requires the gas line to be relocated. 

 

The Town requested permission from Xcel to allow the relocation of the gas line through an Xcel pre-approved subcontractor as part of the Town of Erie’s roadway construction contract. Additionally, the Town offered to pay for an Xcel inspector to be onsite during the work effort. Xcel denied this request and they must manage the contract themselves. They also require the Town to provide approved funding through the contract under consideration in advance of beginning design and relocation services. The cost of the work is estimated to be no more than $742,409.

 

Work on the west side of the roundabout at County Line Road and Austin Avenue cannot be fully completed until the gas line is relocated. A small detour section across the west leg of Austin was installed to temporarily allow traffic to cross the gas line where the depth is still at a safe elevation until the gas line can be lowered and the final intersection layout can be completed. Town staff will work with Xcel to minimize traffic impacts through the duration of the relocation.  


priorities

TOWN COUNCIL PRIORITY(S) ADDRESSED:

Traffic & Road Infrastructure

Growth & Development

Water Cost & Availability

Affordable & Diverse Housing

Increased Commercial Development

Responsible Oil & Gas Development

Preservation of Open Space

Recreation & Community Amenities

Multi-Modal Focus

 

attachments

ATTACHMENT(S):

1.                     Resolution

2.                     Agreement

3.                     Gas line plan and profile exhibit