Title: A Resolution of the Town Council of the Town of Erie Approving an Agreement for Professional Services with RockSol Consulting Group, Inc., for the Downtown Infrastructure Improvement Alley Final Design
Attachments: 1. Resolution 25-006, 2. Agreement, 3. Vicinity Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: 

Title

A Resolution of the Town Council of the Town of Erie Approving an Agreement for Professional Services with RockSol Consulting Group, Inc., for the Downtown Infrastructure Improvement Alley Final Design

 

Body

 

DEPARTMENT:                        Public Works

Department

 

PRESENTER(S):                       David Pasic, Director of Public Works

                                                               Jonathan Williams, Civil Engineer

First Name Last Name, Title

 

FISCAL SUMMARY:

Cost as Recommended:                                           $286,690.72

Balance Available:                                                                 $1,440,000

Budget Line Item Number:                       340-70-110-605000-150000

New Appropriation Required:                       No

 

POLICY ISSUES:

None

 

STAFF RECOMMENDATION:

Recommendation

Approve the Resolution authorizing the final design Professional Services Agreement with RockSol Consulting Group.

End

 

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

Alleys on the 500 and 600 blocks east and west of Briggs Street are in unimproved right of way, lacking proper drainage conveyance, and can be difficult to access following storm events. The unimproved alley conditions also require more ongoing maintenance from Town staff. Both business and residents use the alley for deliveries and access to properties daily. 

 

A 30% design plan set was completed for the Town by RockSol Consulting through Urban Renewal Authority funds in early 2023. With this agreement, the Town will take the 30% design to completion with the intent of installing storm drainage facilities in the alleys and install curb, gutter, and asphalt. The alley section is generally 16 feet wide, but in some locations, it narrows to 12.5 feet wide. Completion of the design work, bidding, and construction management services will be facilitated through the Public Works Department. Staff anticipates there will be minimal utility relocation necessary for this project. Staff also anticipates design to be complete by the end of 2025, apart from securing property easements needed for access to various lots. Construction will likely begin in 2026 once easements have been acquired. As noted above, the total available budget for design and construction of this project is $1,440,000.  The design effort will cost $286,690.72.

 

 

COUNCIL PRIORITY(S) ADDRESSED:

ü                     Attractive Community Amenities

ü                     Engaged and Diverse Community

ü                     Prosperous Economy

ü                     Well-Maintained Transportation Infrastructure

ü                     Small Town Feel

ü                     Safe and Healthy Community

 

ATTACHMENT(S):                      

1.                     Resolution 25-006

2.                     Contract

3.                     Vicinity Map