Title: A Resolution of the Town Council of the Town of Erie Approving Change Order to Construction Contract with Ralph L. Wadsworth Construction Company, LLC
Attachments: 1. Resolution 24-187, 2. Change Order, 3. Agreement 07/23/2024
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT:

Title

A Resolution of the Town Council of the Town of Erie Approving Change Order to Construction Contract with Ralph L. Wadsworth Construction Company, LLC

Body

 

DEPARTMENT:                        Public Works

Department

 

PRESENTER(S):                       Todd Fessenden, Utilities Director

                                                               David Pasic, Public Works Director

First Name Last Name, Title

 

FISCAL SUMMARY:

Cost as Recommended:                                           $ 197,846.30

Balance Available:                                                                 $ 237,937.70

Budget Line Item Number:                       530-70-110-605000-100435

New Appropriation Required:                       No

 

POLICY ISSUES:

A change order is needed to safely complete the Erie Airport Apron, Taxiway and Runway Rehabilitation project. This serves the Council’s goal for maintaining infrastructure. Federal Aviation Administration (90%) and Colorado Department of Aviation (5%) grant funding will be used for this project and the current change order request, leaving the Town responsible to pay our 5% of the cost.

 

STAFF RECOMMENDATION:

Recommendation

Approve the Resolution

 

End

 

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

On Jul. 23, 2024, the Town Council executed a construction contract with Ralph L. Wadsworth Construction Company, LLC (Wadsworth) for the Erie Airport Apron, Taxiway and Runway Rehabilitation. The project is funded through the Federal Aviation Administration (FAA) for 90%, Colorado Division of Aeronautics (CDOA) for 5%, and the Town of Erie for 5%.

 

When Wadsworth commenced the project they discovered numerous areas of the ramp and taxiway where no base course was used to under the original concrete. The project team was faced with the decision to either increase the scope and cost of the project by removing the existing clay soils and adding base course to ensure the life of new concrete placements or reduce the number of concrete panels being replaced.

 

Given that we had a contractor mobilized and an active FAA/CDOA project and increased funding by those parties, the group agreed that a change order for the earthwork was the most prudent course of action. The overall change order is $197,086.84 and the Town’s 5% share of that expense is $9,854.35. We will budget for the full change order but will be reimbursed for 95% of the cost by FAA and CDOA.

 

Cost Summary

                     Construction                     $826,846.30

                     Change Order #1                     $197,086.84

                     Total                     $1,023,933.14

 

Funding

                     FAA                     $177,378.15

                     CDOA                     $9,854.34

                     Town                     $9,854.35

                     Total                     $197,086.84

 

COUNCIL PRIORITY(S) ADDRESSED:

ü                     Well-Maintained Transportation Infrastructure

ü                     Safe and Healthy Community

ü                     Effective Governance