Title: A Resolution of the Town Council of the Town of Erie Approving a Construction Contract with JOC Construction, LLC for the Kenosha Farms Culvert Repairs
Attachments: 1. Resolution 25-101, 2. Contract, 3. Budget Change Request
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: 

Title
A Resolution of the Town Council of the Town of Erie Approving a Construction Contract with JOC Construction, LLC for the Kenosha Farms Culvert Repairs

 

Department

DEPARTMENT:                     Utilities

Presenter

PRESENTER(S):                     Todd Fessenden, Utilities Director

end

 

Time

Fiscal
FISCAL SUMMARY:

Cost as Recommended:                      $ 641,924.36

Balance Available:                                            $ 515,000.00 + $127,000 transfer request

Fund                                                                                     Storm Drainage Operating Fund

Budget Line Item Number: 520-75-110-605000-257520

Budget Transfer:                                           $127,000 from 520-75-110-605000-100149

New Appropriation Required:  No


Policy

POLICY ISSUES:

Money budgeted to complete the project. This serves the Council’s goal for maintaining infrastructure. Delaying this service would result in additional deterioration and additional, even higher, future costs.

 

Recommendation

STAFF RECOMMENDATION:

Approve the resolution

Body

SUMMARY/KEY POINTS

                     Culverts need replacement before Street Maintenance Project construction this summer

                     Street Maintenance Project contract approved by Council on May 27, 2025

 

BACKGROUND OF SUBJECT MATTER:

The 2025 capital budget includes funds for culvert replacements due to erosion, failure and/or reached its useful life cycle. When culverts tend to fail, they can cause catastrophic situations.  For example, a few years ago there was a culvert that ran under Erie Parkway and the structural integrity of the pipe was compromised, causing flow to exit the pipe in ways it was not intended to, therefore causing erosion around the pipe leading to a sinkhole in one of our main arterial roads in town - which lead to costly repairs and a high impact on traffic including emergency vehicles.

 

Using the Gordian Job Order Contracting program, the Town received a bid from JOC Construction for 641,924.36 to replace two culverts on Allen Avenue and Nonaham Lane in Kenosha Farms.

 

Our goal is to complete this project before the Street Maintenance project begins, which will involve a mill and overlay of the roadway. If this culvert project gets delayed, we could potentially have negative impacts to the new roadway after the completion of the street maintenance project.

 

The project is over the existing budget. In order to complete this project, Staff asks Council to transfer $127,000 to Budget Line Number 520-75-110-605000-257520 (Culvert Replacement) from (520-75-110-605000-100149) (Drainage Facility M&R).

 


priorities

TOWN COUNCIL PRIORITY(S) ADDRESSED:

Attractive Community Amenities

Engaged and Diverse Community

Prosperous Economy

Well-Maintained Transportation Infrastructure

Small Town Feel

Safe and Healthy Community

Effective Governance

Environmentally Sustainable

Fiscally Responsible

 