Skip to main content
Town of Erie
File #: 2026-134    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 2/10/2026 In control: Town Council
On agenda: 2/24/2026 Final action:
Title: A Resolution of the Town Council of the Town of Erie Approving the Construction Contract with Geo-Solutions for the Erie Lake Dam Rehabilitation Project
Attachments: 1. Resolution 26-032, 2. Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: 

Title
A Resolution of the Town Council of the Town of Erie Approving the Construction Contract with Geo-Solutions for the Erie Lake Dam Rehabilitation Project

 

Department

DEPARTMENT:                     Utilities


Presenter

PRESENTER(S):                     Bruce Chameroy, Water and Wastewater Division Manager

Weston Ring, Utilities Project Manager
end

 

Time

TIME ESTIMATE: 0 minutes
end

For time estimate: please put 0 for Consent items.

 

Fiscal
FISCAL SUMMARY:

Cost as Recommended:                                           $1,862,021

Balance Available:                                                                 $1,000,000

Fund                                                                                                          Water Fund

Line Item Number:                                                                500-75-110-605000-257502

New Appropriation Required:                       Yes - $2,427,035.00 in First Supplemental Rollover


Policy

POLICY ISSUES:

Town Council must approve spending of this amount according to the Purchasing Policy and Town Charter.

 

Recommendation

STAFF RECOMMENDATION:

The staff recommends approving this construction contract.

Body

SUMMARY/KEY POINTS

                     This item is in front of Council to approve the contract amount of $1,862,021 to complete the construction required for the Erie Lake Dam Rehabilitation project.

                     HDR has completed the engineering and design work on this project and it is ready to move into construction.

                     The project is on a condensed timeline due to the need for work to be completed before the summer of 2026.

 

BACKGROUND OF SUBJECT MATTER:

The Colorado Dam Safety, Office of the State Engineer (SEO) performed the annual inspection for Erie Lake Dam on Sept. 26, 2022 and observed pooling water at the downstream toe of the dam, located along the southwest portion of the embankment. SEO instructed Town staff to institute a daily monitoring plan and to update data on a shared file with photographs and measurements. On Sept 27, 2022, the Utilities staff cleared vegetation from the wet area and identified the active source of seepage. The Town’s Utilities Director contacted HDR for support on evaluating the seepage issue. HDR was contracted with the Town to perform a data/records review of pertinent available documentation, perform an onsite dam examination, and deliver a technical memo of findings and recommendations.

Since this time, HDR has completed the design and engineering for dam rehabilitation. The Town formally requested bids for construction and determined Geo-Solutions to be the most capable contractor to complete this work for the Town.


priorities

.

attachments

ATTACHMENT(S):

1.                     Resolution

2.                     Construction Contract