File #: 18-100    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 2/27/2018 In control: Town Council
On agenda: 3/13/2018 Final action:
Title: A Resolution Authorizing the Award of a Consultant Contract to JR Engineering, LLC for the Zone 3 Waterline Improvements Phase 2 in The Amount of $116,713.00 and a Contingency amount to not exceed $23,287.00.
Attachments: 1. Resolution, 2. Vicinity Map.pdf, 3. Consultant Agreement Zone 3 Waterline Extension P-2 .pdf
Related files: 20-227, 19-510, 20-075
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: CONSENT

Title

A Resolution Authorizing the Award of a Consultant Contract to JR Engineering, LLC for the Zone 3 Waterline Improvements Phase 2 in The Amount of $116,713.00 and a Contingency amount to not exceed $23,287.00.

Body

DEPARTMENT:                                          Planning & Development

 

PRESENTER/PREPARER:                     Todd Bjerkaas, Director of Planning & Development

Russell Pennington, Town Engineer

                                                                                                         Wendi Palmer, Civil Engineer

FISCAL INFORMATION:

Cost as Recommended:                                          $140,000.00

Balance Available:                                                               $550,000.00

Fund:                                                                                                         Water

Budget Line Item Number:                                           510.70.110.605000.100228

New Appropriation Required:                     No

 

STAFF RECOMMENDATION:

Recommendation

Approve the Resolution to award said contract, authorize the appropriate Town officer to execute said contract, and authorize Staff to expend contracted funds and contingency funds.

 

End

SUMMARY AND BACKGROUND OF SUBJECT MATTER:

 

The 2013 Water Master Plan identifies the need for a Zone 3, 30-inch and 24-inch transmission waterline from the Water Treatment Plant to the Zone 3 Water Storage Tank Site.  The transmission waterline is needed to meet the existing and future demand for water supply to the Town’s 1.5-MG and 4-MG water storage tanks for Zone 3, and the Zone 4A pump station. 

 

The 2018 Water Capital Budget has funds appropriated for designing the Zone 3 Waterline Improvements Phase-2. 

 

In 2017, the middle section or Phase 1 of this transmission line was constructed from the intersection of Vista Parkway and County Line Road to Vista Parkway just north of Vista Ridge Subdivision.

 

The remaining sections will be designed at this time.  Town Staff does anticipate that there might be the need to bid the construction in two projects depending upon easement acquisition and permitting requirements.

 

A Request for Proposal was posted on the Town’s website on January 10, 2018 to ensure that local consultants were notified about this project. 

 

The following schedule was used for consultant selection:

 

Request for Proposal Issued                                          January 10, 2018

Pre-Proposal Meeting                                                               January 17, 2018

Proposals Due                                                                                    February 6, 2018

Consultant Selected                                                                                    February 28, 2018

 

The Town received 7 proposals on February 6, 2018. Staff reviewed all 7 proposals in detail. The proposals were ranked, and the fees for the top 4 proposals were opened. The following are the fees for the top 4 proposals:

 

Fee Proposal Information

                     

JR Engineering                                                                                                         $116,713.00

JVA Consulting Engineers                                                                                    $133,800.00

Merrick and Company                                                                                    $166,325.00

Burns & McDonnell                                                                                                         $248,619.00

 

Staff is recommending awarding JR Engineering, LLC. this project based on their qualifications, approach to the project, and design cost. Past projects that JR Engineering, LLC worked on with the Town include; the first phase of the Zone 3 Waterline Improvements, the Vista Ridge Commercial Access onto State Highway 7, the State Highway 7 Sidewalk and the conceptual design for County Line Road within Erie’s planning area.

 

Project Budget Summary

                     Contract                     $116,713.00

                     Contingency (20%)                     $  23,287.00

                     Total                     $140,000.00

 

Remaining funds will be used in the construction of the project.  The Construction project will be presented to the Board early next year.

 

Project Schedule

                     Notice of Award                     March 14, 2018

                     Preliminary Design                     Summer 2018

                     Final Design                     Fall 2018

                     Anticipated Project bid                     Early 2019

                     Anticipated Construction Complete                     Fall 2019

 

ATTACHMENTS:                      

 

a.                     Resolution

b.                     Consultant Agreement

c.                     Vicinity Map