SUBJECT: CONSENT AGENDA
Title
Consideration of A Resolution Authorizing Award of a Construction Contract To Spiegel Industrial, LLC, For the 1.5 MG Zone 3 Water Storage Tank Improvements Project In The Amount of $460,000; And Setting Forth Details In Relation Thereto.
Body
DEPARTMENT: Public Works
PRESENTER/PREPARER: Gary Behlen, Public Works Director
Russell Pennington, Deputy Public Works Director
Wendi Palmer, Civil Engineer
FISCAL INFORMATION:
Cost as Recommended: $522,000
Balance Available: $604,678 (Pending 2015 funds to be rolled-over)
Fund: Water
Budget Line Item Number: 500-70-110-605000-100137
New Appropriation Required: No
STAFF RECOMMENDATION:
Recommendation
Approving the Resolution to award said contract, authorizing the appropriate Town officer to execute said contract, authorizing Staff to expend contracted funds and contingency funds.
End
SUMMARY AND BACKGROUND OF SUBJECT MATTER:
The 2016 budget includes funds to design and construct improvements to the 1.5 MG Zone 3 Water Storage Tank.
During an inspection of the 1.5 mg water tank in 2014, it was discovered that there were leaks at the pipe penetrations of the tank. A remedial repair was done in 2014 using divers to complete the repair. At that time it was not practical to drain the tank for a permanent repair.
The Town completed the construction of the 4 MG Zone 3 Water Storage Tank early spring of 2015. With the new 4 MG tank operational, Town Staff has been able to take the 1.5 MG tank out of service and further assess the repairs needed to correct the leaks. In addition to repairing the leaks, other improvements to the tank have been designed and include adding a mixing system and lining the concrete tank. Both the mixing system and tank liner will help with water quality in the tank and help the tank operate in the same manner as the new 4 MG tank next to it.
Burns & McDonnell assisted the Town in preparing the design and bid documents for the improvements.
An Invitation to bid was posted on the Town’s website for the 1.5 MG Zone 3 Water Storage Tank Improvements Project on May 20, 2016 to ensure that local contractors were notified about this project. No Erie contractors submitted bids.
The following bids were received on June 17, 2016:
Bid Information:
Contractor Bid Amount
Spiegel Industrial, LLC $ 460,000.00
Fischer Construction, Inc. $ 549,619.00
Glacier Construction Co., Inc. $ 754,000.00
Aslan Construction, Inc. $ 757,455.00
Principal Industrial Services, Inc. $ 783,250.00
Meyers and Sons Construction LP $ 947,000.00
Engineer’s Estimate $ 618,007.00
The low bidder is Spiegel Industrial, LLC (Spiegel). Spiegel has field offices in Johnstown and Grand Junction with their CEO office in Steamboat Springs. Spiegel Industrial, LLC was formed in September 2012. Prior to that, the company was known as Spiegel and Son, Inc., which was established in Colorado in 1995.
Spiegel has performed multiple tank lining projects for several municipalities and water districts in Colorado. Examples are: Meeker, Grand Junction, Town of Parachute, Table Mountain Water & Sewer District and Eagle River Water & Sewer District. Town Staff has reviewed the bid, reviewed the project with the Contractor, and had Burns & McDonnell contact references.
Staff is recommending awarding the construction contract for the 1.5 MG Zone 3 Water Storage Tank Improvements Project to Spiegel Industrial, LLC, in the amount of $460,000.
Summary
Construction Contract $ 460,000
Contingency (20%) $ 92,000
Total $ 552,000
Project Schedule
Notice of Award June 29, 2016
Notice to Proceed July 13, 2016
Construction Complete Fall, 2016