Legislation Details

File #: 2026-41    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 12/30/2025 In control: Town Council
On agenda: 1/27/2026 Final action:
Title: A Resolution of the Town Council of the Town of Erie Approving a Professional Services Agreement Task Order for Kimley-Horn and Associates for Design Services for Compass Neighborhood Park
Attachments: 1. Resolution 26-022, 2. Compass Neighborhood Park Concept Plan, 3. Task Order
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: 

Title
A Resolution of the Town Council of the Town of Erie Approving a Professional Services Agreement Task Order for Kimley-Horn and Associates for Design Services for Compass Neighborhood Park

 

Department

DEPARTMENT:                     Parks & Recreation


Presenter

PRESENTER(S):                     Luke Bolinger, Director of Parks & Recreation

Kathy Kron, Development & Neighborhood Services Division Manager
end

 

Time

TIME ESTIMATE: 0 minutes
end

 

Fiscal
FISCAL SUMMARY:

Cost as Recommended:                                           $499,300

Balance Available:                                                                 $3,350,000

Fund                                                                                                          Parks Improvement Impact Fund

Line Item Number:                                            320-50-110-605000-100292

New Appropriation Required:                       No


Policy

POLICY ISSUES:

Town Council must approve expenditures of this amount according to the Town Charter.

Recommendation

 

STAFF RECOMMENDATION:

Approve the resolution.

Body

SUMMARY/KEY POINTS

•                     This resolution allows staff to move forward with design services and complete construction drawings for Phase 1 of Compass neighborhood park.

•                     Construction of Phase 1 of Compass neighborhood park was identified as a high priority from the community during the 2026 budget process.

•                     Council approval is needed to execute a task order for design services as part of the Landscape Architecture On-Call Contract.

 

BACKGROUND OF SUBJECT MATTER:

In 2022 and 2023 staff and design consultant, Kimley-Horn & Associates, conducted a community engagement process and developed a Concept Plan for Compass neighborhood park that was adopted by the then Board of Trustees in March of 2023. The plan was designed around four core principles: inclusivity, education, sustainability, and activities. Features of the plan resulting from this guidance include an inclusive, nature-based play area, sport courts, artificial turf multi-purpose fields, a challenger field, educational display gardens, as well as comfort amenities such as parking, restrooms, shelters, and picnic areas.

 

In 2023 and 2024 staff continued to work with Kimley-Horn to further develop the plan to the design development level. These plans provide site specific development of the concept plans and further evaluation of the estimated cost for development of the park.

 

The cost estimate for full development of the park is approximately $12,000,000. Due to insufficient funds in the Parks Improvement Impact Fund and a high level of interest from the community in implementing park improvements, Council directed staff to move forward with phasing the project and appropriated funds in the 2026 Budget.

 

The 2026 Budget includes $3,350,000 to implement phase 1 of the project. Construction documents will take approximately six to eight months to complete, after which staff will bring forward a construction contract for a general contractor to begin construction in Q4 of 2026.


priorities

.

attachments

ATTACHMENT(S):

1.                     Resolution

2.                     Compass Neighborhood Park Concept Plan

3.                     Task Order