Legislation Details

File #: 2026-352    Version: 1 Name:
Type: Consent Agenda Status: Agenda Ready
File created: 5/21/2026 In control: Town Council
On agenda: 6/9/2026 Final action:
Title: A Resolution of the Town Council of the Town of Erie Approving the Construction Contract with Colorado Boring Company for the Fiber from Water Plant to Tank Site Project
Attachments: 1. Agreement, 2. Resolution 26-110
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

SUBJECT: 

Title
A Resolution of the Town Council of the Town of Erie Approving the Construction Contract with Colorado Boring Company for the Fiber from Water Plant to Tank Site Project

 

Department

DEPARTMENT:                     Utilities


Presenter

PRESENTER(S):                     Todd Fessenden, Utilities Director

end

 

Time

TIME ESTIMATE: 0 minutes
end

For time estimate: please put 0 for Consent items.

 

Fiscal
FISCAL SUMMARY:

Cost as Recommended:                                           $587,000.00

Balance Available:                                                                 $675,000.00

Fund                                                                                                          Water Fund

Line Item Number:                                            500-75-110-605000-247009

New Appropriation Required:                       No


Policy

POLICY ISSUES:

This resolution proposes using funds that are budgeted to complete the fiber communications connection between the Lynn R. Morgan Water Treatment Facility and the Zone 3 tanks. This serves the Council’s goal for maintaining infrastructure.

 

Recommendation

STAFF RECOMMENDATION:

Approve the resolution.

Body

SUMMARY AND BACKGROUND OF SUBJECT MATTER

The 2026 Capital Budget includes funds for the fiber communications connection between the Lynn R. Morgan Water Treatment Facility and the Zone 3 tanks. The Town currently uses radio signal to communicate with and monitor the Zone 3 tanks. Staff requested bids using the Rocky Mountain E-Purchasing system. Bids were received on May 8, 2026. The Town received nine bids and one material bid.

 

The project includes the design and construction of a fiber connection between the Town’s water treatment facility and the Town’s tank site west of WCR 7. This project includes the design for the alignment of approximately 9,200 LF of new 2” conduit, including pull boxes a minimum of every 1,000 feet. The installation of approximately 26,000 LF of 48-strand fiber. The alignment includes approximately 10,000 LF of existing 2” conduit with pull boxes, 6,800 LF of existing 3” conduit with pull boxes, approximately 6 roadway crossings, a crossing of a 28” Northern Colorado Water Conservation District waterline, a crossing of Coal Creek, installation of fiber patch panels in the pump station at the water treatment facility and in the pump station at the tank site.

 

The lowest responsive bidder was Colorado Boring Company with a bid of $493,485.00.

 

Cost Summary

                     Original Contract                     $493,485.00

                     Contingency (25%)                     $93,515.00

                     Total                     $587,000.00

 

 

attachments

ATTACHMENT(S):

1.                     Resolution

2.                     Contract